File #: 19-0261    Version: 1
Type: Consent - Staff Report Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 6/18/2019 Final action:
Title: Accept as Complete the Morningside Drive Rehabilitation Project by FS Contractors, Inc.; Authorize Filing Notice of Completion with the County Recorder; and Release the Retention Amount of $6,678.40 (Public Works Director Katsouleas). APPROVE
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Bruce Moe, City Manager

FROM:
Stephanie Katsouleas, Public Works Director
Prem Kumar, City Engineer
Adilia Miller, Senior Civil Engineer

SUBJECT:Title
Accept as Complete the Morningside Drive Rehabilitation Project by FS Contractors, Inc.; Authorize Filing Notice of Completion with the County Recorder; and Release the Retention Amount of $6,678.40 (Public Works Director Katsouleas).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council formally accept as complete the Morningside Drive Rehabilitation Project constructed by FS Contractors, Inc.; authorize filing a Notice of Completion with the County Recorder's Office; and approve the release of retention for $6,678.40 to FS Contractors, Inc.

FISCAL IMPLICATIONS:
The Morningside Drive Rehabilitation Project construction contract award was $145,892, with an authorized construction contingency amount of $29,178, for total construction budget of $175,070. The work was successfully completed under budget for $133,568. The remaining unexpended balance will be returned to the Streets and Highways Fund for re-appropriation for a future project.

BACKGROUND:
On February 5, 2019, City Council awarded a construction contract to FS Contractors, Inc. for the construction of the Morningside Drive Rehabilitation Project. Morningside Drive, between 10th Place and Manhattan Beach Blvd., is a Portland Cement Concrete (PCC) street that had compromised sections and required partial conventional slab replacement to restore its structural integrity. The work included full depth removal of the structurally damaged sections of concrete and replacement with new concrete that was tied in at designated joints.

DISCUSSION:
Construction began on March 7, 2019 and was completed on April 16, 2019. The Contractor has completed all contract work and is now requesting formal acceptance of ...

Click here for full text