Title: Formally Accept as Complete the Cycle 1 Storm Drain Catch Basin Insert Project Constructed by G2 Construction, Inc., Authorize Filing a Notice of Completion with the County Recorder's Office, and Approve the Release of Retention for $5,479.22 to G2 Construction (Public Works Director Katsouleas). APPROVE
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Mark Danaj, City Manager

FROM:
Stephanie Katsouleas, Public Works Director
Prem Kumar, City Engineer
Tim Birthisel, Project Engineer

SUBJECT:Title
Formally Accept as Complete the Cycle 1 Storm Drain Catch Basin Insert Project Constructed by G2 Construction, Inc., Authorize Filing a Notice of Completion with the County Recorder's Office, and Approve the Release of Retention for $5,479.22 to G2 Construction (Public Works Director Katsouleas).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council:

1. Formally accept as complete the Cycle 1 Storm Drain Catch Basin Insert Project constructed by G2 Construction Inc.;
2. Authorize Filing of the appropriate Notice of Completion with the County Recorder's Office; and
3. Approve the release of retention for $5,479.22 to G2 Construction.
Body
FISCAL IMPLICATIONS:
The original Cycle 1 Storm Drain Catch Basin Insert Project construction contract award amount was $123,635, with an additional contingency amount of $12,364.00. The work was successfully completed under budget for $109,584.42.

BACKGROUND:
On February 7, 2017, City Council awarded a construction contract to G2 Construction, Inc. for $123,635.00 to install connector pipe screen (CPS) and automatic retractable screen (ARS) units at catch basins citywide, which is as one implementation measure to meet current MS4 NPDES Permit requirements for trash.

DISCUSSION:
Installations began on April 3, 2017 and were completed on June 27, 2017. The original contract called for installing either connector pipe screen units (internal mounting) or automatic retractable screen units (external mounting) at 170 locations. However, after further analysis, it was determined that 51 catch basin locations could be "bundled" together by installing one larger trash collection device downstream at a single collection point in ...