Skip to main content
Manhattan Beach Logo
File #: 21-0035    Version: 1
Type: Consent - Staff Report Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 2/2/2021 Final action:
Title: Consideration of a Resolution Approving Amendment No. 2 to the Professional Services Agreement with IDS Group, Inc. for Additional Design Services for the Kiln Project at Live Oak Park at a Cost Not-to-Exceed $15,000 (Interim Public Works Director Tai and Parks and Recreation Director Leyman). APPROVE RESOLUTION 21-0013
Attachments: 1. Resolution No. 21-0013, 2. Amendment No. 2 - IDS Group, Inc., 3. Agreement and Amendment No. 1 - IDS Group, Inc., 4. Current Schematic Design, 5. Project Map

TO:

Honorable Mayor and Members of the City Council

 

THROUGH:

Bruce Moe, City Manager

 

FROM:

Carrie Tai, Interim Public Works Director

Mark Leyman, Parks and Recreation Director

Prem Kumar, City Engineer

Mamerto Estepa Jr., Senior Civil Engineer

 

SUBJECT:Title

Consideration of a Resolution Approving Amendment No. 2 to the Professional Services Agreement with IDS Group, Inc. for Additional Design Services for the Kiln Project at Live Oak Park at a Cost Not-to-Exceed $15,000 (Interim Public Works Director Tai and Parks and Recreation Director Leyman).

APPROVE RESOLUTION 21-0013

Line

_________________________________________________________

Recommended Action

RECOMMENDATION:
Staff recommends that City Council approve Amendment No. 2 to the Professional Services Agreement with IDS Group, Inc. for additional design services for the Kiln Project at Live Oak Park, at a cost not-to-exceed $15,000.

 

FISCAL IMPLICATIONS:

The original contract amount for the Kiln Project was $49,815. The additional services to be rendered under Amendment No. 2 will increase the contract amount by $15,000 to $64,815. Because the total contract amount exceeds the City Manager’s awarding authority per the City’s purchasing policy, Council approval of Amendment No. 2 is required. The additional services can be paid for from the Ceramic Studio Renovation budget, which has a current balance of $259,500.   

 

BACKGROUND: 

The existing Geil ceramic kiln at Live Oak Park is over 40 years old and nearing the end of its useful life. For much of its life, it served to fire the bulk of the ceramics projects produced by students of the City’s Ceramics Program. However, the kiln has deteriorated due to age and now requires frequent repairs to keep it operating.  In summary, it can no longer reliably meet the needs of the Ceramics program.

 

In 2018, the Parks and Recreation Department purchased a new Geil kiln, with the intent of replacing the existing unit as a primary firing kiln and converting the existing kiln into an experimental kiln. The experimental kiln would use alternative firing method (soda feldspar), which can create a unique glaze finish on ceramics projects that is not offered in ceramic studios in the South Bay.

 

The new kiln would be installed outdoors adjacent to the existing ceramic kiln enclosure and beneath an open, covered structure. Because the California Building Code requires building permits and formal engineering for the concrete foundation and open, covered structure, the Parks & Recreation department reached out to the Public Works department for support. 

 

The City issued a Request for Proposal in early 2019 to secure a design consultant and in July 2019 finalized an agreement with IDS Group, Inc. to perform design services.  IDS Group, Inc. worked with the Parks and Recreation, Public Works, and Community Development departments to develop a design concept for the project based on a schematic design produced by Parks and Recreation.  This design included the construction of a new concrete pad, installation of a steel awning, removal and relocation of existing fencing, and location of new gas and electrical connections. IDS proceeded with developing plans, specifications and estimate (PS&E) for construction. During PS&E development, IDS Group, Inc. revised the design to meet the needs initially shared by the Parks and Recreation Department. The plans were then submitted to the Building and Safety division and received approval.

 

Upon final review of the approved plans approved, it was discovered that while the design included all the elements from the original concept, the design did not fully achieve adequate protection of the new kiln from the elements or for upgrading the existing gas service to the existing kiln enclosure.

 

IDS Group, Inc. generated a proposal to revisit some of the conceptual design issues and revise the construction documents and calculations. The work effort will cost $15,000.  

 

DISCUSSION:

The Ceramics Program is a popular, well-utilized Parks and Recreation Program. Over the past few years, the enrollment has nearly doubled. Prior to COVID-19, the Ceramics Studio would see as many as 200 students per week. Since COVID-19, students work on projects at home and drop-off their projects for kiln firing. Despite the pandemic, the program continues to serve upwards of 100 students per week. There continues to be a demand for the City to operate a reliable, large capacity kiln.

 

Amendment No. 2 will provide design services geared towards minimizing the kiln’s exposure to environment elements, which will maximize its life. The key area to protect is the rear of the kiln, where the electrical and gas lines connect to unit. The project design elements that will be considered include, but are not limited to lowering the height of the awning, controlling runoff from the roof by installing a roof gutter or changing the pitch, installing a wall at the rear of the awning and adding a screen to the chain link fence behind the kiln structure. Lastly, the design will accommodate providing a new gas line and accessible shutoff to the existing kiln enclosure.  While the kiln is designed for outdoor installation, every effort should be made to maximize the City’s investment and ensure that the kiln can serve the Ceramics Program for many years.

 

Following approval of the Amendment No. 2, the projected schedule for the project is as follows:

 

                     Milestone                                                                                                                                                   

                     Resume Design                                                                                                                                                   March 2021

                     Plans Resubmitted to Building Safety                                                                                    May 2021

                     Advertise for Bid                                                                                                                                                   July 2021

                     Open Bids                                                                                                                                                                        September 2021

                     Project Award                                                                                                                                                   November 2021

                     Notice to Proceed with Construction                                                                                     December 2021

 

PUBLIC OUTREACH:

The Kiln Project is included on the Capital Improvement Projects map and plan, which are found on the Engineering Division web page on the City website.

 

As part of the project, the Contractor will be required to place a project information sign to inform the public of the project and detour pedestrians around the work area during construction.

 

ENVIROMENTAL REVIEW:

The City has reviewed the proposed project for compliance with the California Environmental Quality Act and has determined that the project qualifies for a Categorical Exemption pursuant to Section 15311 Accessory Structures of the State CEQA Guidelines.

 

LEGAL REVIEW:

The City Attorney has reviewed this report and determined that no additional legal analysis is necessary.

 

ATTACHMENTS:

1.                     Resolution 21-0013

2.                     Amendment No. 2 - IDS Group, Inc.

3.                     Agreement and Amendment No. 1 - IDS Group, Inc.

4.                     Current Schematic Design

5.                     Project Map