TO:
Honorable Mayor and Members of the City Council
THROUGH:
Bruce Moe, City Manager
FROM:
Stephanie Katsouleas, Public Works Director
Prem Kumar, City Engineer
Anastasia Seims, Senior Civil Engineer
SUBJECT:Title
Consider the Following:
1) Adopting a Resolution Awarding a Construction Agreement to C.A Rasmussen, Inc. for the Sepulveda Bridge Widening Project for $8,791,040; Authorizing the City Manager to Approve Additional Work if Necessary, for up to $879,105; and Approving the Plans and Specifications for the Project;
2) Adopting a Resolution Awarding a Construction Management Services Agreement with S2 Engineering, Inc. for the Sepulveda Bridge Widening Project for $1,689,704;
3) Adopting a Resolution Approving Amendment No. 7 to the Professional Design Services Agreement with HDR Engineering, Inc. for the Sepulveda Bridge Widening Project for $424,546 (Public Works Director Katsouleas).
ADOPT RESOLUTION NOS. 20-0082, 20-0083 AND 20-0084
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council adopt:
1. Resolution No. 20-0082 awarding a construction agreement to C.A Rasmussen, Inc. for the Sepulveda Bridge Widening Project for $8,791,040, authorizing the City Manager to execute the Agreement; authorizing the City Manager to approve additional work, if necessary, for up to $879,105; and approving the Plans and Specifications for the Project;
2. Resolution No. 20-0083 awarding a Construction Management Services Agreement with S2 Engineering, Inc. for the Sepulveda Bridge Widening Project for $1,689,704; and
3. Resolution No. 20-0084 approving Amendment No. 7 to the Professional Design Services Agreement with HDR Engineering, Inc. for the Sepulveda Bridge Widening Project for $424,546.
FISCAL IMPLICATIONS:
A combination of federal and local funds is currently available for this Project in the approved budget. No additional funding appropriation is necessary. The agreements with...
Click here for full text