Consider: 1) Adopting Resolution 19-0117: Awarding a Construction Agreement to PALP, Inc. DBA Excel Paving Company for the Street Resurfacing Project - Cycle 1 for $1,329,859; Approving the Plans and Specifications for the Project; and Authorizing the City Manager to Approve Additional Work, if Necessary, for up to $164,903; 2) Adopting Resolution No. 19-0118 Awarding an Inspection Services Agreement to Quantum Quality Consulting, Inc. for the Project for $75,250; and 3) Appropriating $108,021 from the Gas Tax Fund Unreserved Fund Balance (Public Works Director Katsouleas).
a) ADOPT RESOLUTION NOS. 19-0117 AND 19-0118 APPROVING AGREEMENTS
b) APPROPRIATE FUNDS
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council:
1. Adopt Resolution No. 19-0117:
a. Awarding a construction agreement to Palp, Inc. DBA Excel Paving Company for the Street Resurfacing Project - Cycle 1 for $1,329,859 and authorizing the City Manager to execute the agreement;
b. Approving the Plans and Specifications for the Project; and
c. Authorizing the City Manager to approve additional work, if necessary, for up to $164,903 (12.4% of the agreement).
2. Adopt Resolution No. 19-0118 awarding an inspection services agreement to Quantum Quality Consulting, Inc. for the Project for $75,250 and authorizing the City Manager to execute the agreement.
3. Appropriate an additional $108,021 from the Gas Tax Fund Unreserved Fund Balance for the Project.
FISCAL IMPLICATIONS:
If City Council approves staff's request to appropriate an additional $108,021 from the Gas Tax Unreserved Fund balance, then sufficient funds will be available to complete the project for a total of $1,570,012 using Gas Tax and Proposition ...
Click here for full text