Title: Formally Accept as Complete the Manhattan Beach Pier Utilities and Roundhouse Exterior Improvements Project Constructed by Archico Design Build, Inc. (Public Works Director Katsouleas). APPROVE
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Bruce Moe, City Manager

FROM:
Stephanie Katsouleas, Public Works Director
Prem Kumar, City Engineer
Gilbert Gamboa, Senior Civil Engineer

SUBJECT:Title
Formally Accept as Complete the Manhattan Beach Pier Utilities and Roundhouse Exterior Improvements Project Constructed by Archico Design Build, Inc. (Public Works Director Katsouleas).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council formally accept as complete the Manhattan Beach Pier Utilities and Roundhouse Exterior Improvements Project constructed by Archico Design Build, Inc.
Body
FISCAL IMPLICATIONS:
The Manhattan Beach Pier Utilities and Roundhouse Exterior Improvements Project construction contract award was for $1,692,975, with an authorized construction contingency amount of $169,298, for a total construction budget of $1,862,273. The work was successfully completed for $1,846,775.

BACKGROUND:
On November 21, 2017, City Council awarded a construction contract to Archico Design Build, Inc. for the construction of the Manhattan Beach Pier Utilities and Roundhouse Exterior Improvements Project to address infrastructure that had deteriorated. The Pier utilities work included complete replacement of the water, sanitary sewer main lines and upgrades to electrical power and communications equipment. Amenities such as fish cleaning sinks, life ring cabinets, an emergency call box and exterior surveillance cameras were also installed. The Roundhouse exterior improvements included replacement of the mission tile roof, cupola, weathervane, doors, windows, shutters, louvers and vents. The completed Roundhouse improvements, which also included anti-graffiti paint coating, are consistent with the original architectural character and design of the building.

DISCUSSION:
Construction on the pier utilities and Roundhouse exterior began on January 22, 2018 an...