File #: 19-0076    Version: 1
Type: Consent - Staff Report Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 2/5/2019 Final action:
Title: Resolution No. 19-0017 Awarding a Professional Design Services Agreement to Pacific Advanced Civil Engineering, Inc. (PACE) for the Larsson Street Booster Pump Station Upgrade Project for $138,116 (Public Works Director Katsouleas). ADOPT RESOLUTION NO. 19-0017
Attachments: 1. Resolution No. 19-0017, 2. Agreement - Pacific Advanced Civil Engineering, Inc., 3. Location Map, 4. Budget and Expenditures Summary
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Bruce Moe, City Manager

FROM:
Stephanie Katsouleas, Public Works Director
Prem Kumar, City Engineer
Anastasia Seims, Senior Civil Engineer

SUBJECT:Title
Resolution No. 19-0017 Awarding a Professional Design Services Agreement to Pacific Advanced Civil Engineering, Inc. (PACE) for the Larsson Street Booster Pump Station Upgrade Project for $138,116 (Public Works Director Katsouleas).
ADOPT RESOLUTION NO. 19-0017
Line
_____________________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council adopt Resolution 19-0017 (Attachment) awarding a design services contract (Attachment) to Pacific Advanced Civil Engineering, Inc. (PACE) for the Larsson Street Booster Pump Station Upgrade Project for $138,116 and authorize the City Manager to execute the contract.

FISCAL IMPLICATIONS:
This Larsson Street Booster Pump Station Upgrade Project is in the FY18-19 approved Capital Improvement Program (CIP) and has sufficient funds available to complete the scope of work for $138,116. The Budget and Expenditure Summary is attached (Attachment).

BACKGROUND:
The City's potable water system consists of two pressure zones, the Main Pressure Zone and the Hill Area Pressure Zone, each of which have two booster pumps stations. In the Hill Area Pressure Zone, the primary pump station is the Larsson Booster Pump Station. The City Water Master Plan, completed in October 2010, identified this pump station as needing upgrades in the near future. This project implements those recommendations.

The existing Larsson Booster Pump Station consists of three (3) frame mounted, single stage, horizontal centrifugal pumps, each with variable frequency drive electric motors in a below-ground, precast concrete vault. This pump station also has a permanent standby generator in a second below ground precast concrete vault and an automatic transfer switch in a nearby above grou...