TO:
Honorable Mayor and Members of the City Council
THROUGH:
Bruce Moe, City Manager
FROM:
Stephanie Katsouleas, Director of Public Works
Prem Kumar, City Engineer
Mamerto Estepa, Jr., Associate Engineer
SUBJECT:Title
Resolution No. 18-0157: 1) Awarding a Construction Contract to EBS General Engineering, Inc. for the Marine Avenue Improvement Project for $1,294,521; 2) Authorizing the City Manager Execute the Contract and Approve Additional Work, if Necessary, for up to $129,452; and 3) Approving the Plans and Specifications for the Marine Avenue Improvement Project (Public Works Director Katsouleas).
ADOPT RESOLUTION NO. 18-0157
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council adopt Resolution No. 18-00157 approving the following:
1. Award a construction contract to EBS General Engineering, Inc. for $1,294,521 and authorize the City Manager to execute the contract for the Marine Avenue Improvement Project;
2. Authorize the City Manager to approve additional work, if necessary, for up to $129,452; and
3. Approve the plans and specifications for the Marine Avenue Improvement Project.
.Body
FISCAL IMPLICATIONS:
This project is funded in the Capital Improvement Program utilizing:
* $598,259 from the Streets & Highways Fund;
* $450,414 from the Marine Street Resurfacing Prop C Local Return Fund;
* $223,767 from the Street Resurfacing: Arterial & Collector Roadway Prop C Local Return Fund; and
* $185,000 from the payment received from Plains West Coast Terminals (PWCT) LLC in lieu of the pavement resurfacing requirement along Marine Avenue between Aviation Boulevard and Sepulveda Boulevard.
The Budget and Expenditure summary report is included as an attachment.
BACKGROUND:
The proposed Marine Avenue Improvement Project involves upgrading existing concrete curb ramps to meet existing ADA standards; reconstructing damaged cross gutters; cold milling; cold in-place recycl...
Click here for full text