Title: Resolution No. 18-0091 Approving Amendment No. 1 for $55,000 to Michael Baker International's (MBI) Existing Professional Services Agreement for Additional Engineering and Environmental Services for the Aviation Boulevard at Artesia Boulevard Southbound to Westbound Right Turn Lane Improvement Project (Public Works Director Katsouleas). ADOPT RESOLUTION NO. 18-0091
Attachments: 1. Resolution No. 18-0091, 2. Amendment No. 1 - Michael Baker International, Inc., 3. Agreement - Michael Baker International, Inc. (2017)
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Bruce Moe, City Manager

FROM:
Stephanie Katsouleas, Public Works Director
Prem Kumar, City Engineer

SUBJECT:Title
Resolution No. 18-0091 Approving Amendment No. 1 for $55,000 to Michael Baker International's (MBI) Existing Professional Services Agreement for Additional Engineering and Environmental Services for the Aviation Boulevard at Artesia Boulevard Southbound to Westbound Right Turn Lane Improvement Project (Public Works Director Katsouleas).
ADOPT RESOLUTION NO. 18-0091
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council adopt a resolution authorizing the City Manager to execute Amendment No. 1 for $55,000 to MBI's existing Agreement for additional engineering and environmental services for the Aviation Boulevard at Artesia Boulevard Southbound to Westbound Right Turn Lane Improvement Project.
Body
FISCAL IMPLICATIONS:
The City received a $1,500,000 grant from the Measure R South Bay Highway Program (SBHP) for the Aviation Boulevard at Artesia Boulevard Southbound to Westbound Right Turn Lane Improvement Project. Activities eligible for reimbursement include design, project management, right-of-way acquisition, construction and all other components necessary to complete the project. There is sufficient funding in the budget to perform the work as proposed in Amendment No. 1 for $55,000.

BACKGROUND:
The purpose of the Aviation Boulevard at Artesia Boulevard Southbound to Westbound Right Turn Lane Improvement Project is to provide a dedicated southbound to westbound right-turn lane, which requires widening the west side of Aviation Boulevard north of Artesia Boulevard. Installation of a dedicated right turn lane will help reduce congestion of southbound traffic, improve traffic flow, minimize commuter delay and improve overall safety at this intersection. The project is one of many infrastructure improv...