TO:
Honorable Mayor and Members of the City Council
THROUGH:
Mark Danaj, City Manager
FROM:
Stephanie Katsouleas, Public Works Director
Shawn Igoe, Utilities Division Manager
SUBJECT:Title
Update on Emergency Action Taken by the City Manager regarding the Repair, Replacement and Installation of Equipment at the 23rd Street and Peck Avenue Stormwater Pump Station, and Approval for Continuation of the Emergency Work (Public Works Director Katsouleas).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council:
1. Approve, by 4/5 Vote, continuation of the emergency action taken to repair, replace and install equipment at the 23rd Street and Peck Ave Stormwater Pump Station.
Body
FISCAL IMPLICATIONS:
An appropriation from the General Fund to the Stormwater Fund for $221,415 was required and approved through Resolution No. 17-0015 at the March 21, 2017 City Council meeting to cover the emergency repairs and contingency if needed. If the City’s claim is successful, all or a portion of this amount will be fully reimbursed to the General Fund.
BACKGROUND:
On December 4, 2012, the City Council adopted Resolution No. 12-6422, delegating authority to the City Manager to take action in emergencies pursuant to California Public Contract Code (PCC) Section 22050. Per Resolution No. 12-6422, in the event of an emergency the City Manager may take action to repair public facilities without advertising for bids if the repair is in the public interest and necessitates the immediate expenditure of public money to safeguard life, health or property.
On March 8, 2017, the City approved an emergency declaration for needed repairs to the stormwater pump station at 23rd Street and Peck Ave and shortly thereafter adopted Resolution No. 17-0015, approving the agreement between the City of Manhattan Beach and Ellison Environmental Inc. (dba Fluid Resource Management (Contractor)) to complete those repairs.
Once approved, the contractor immediately removed the motor, pump and other housing equipment that was damaged, and ordered materials that would be needed to complete the repair, including electrical and switch appurtenances.
DISCUSSION:
As of May 2, 2017 City Council meeting, the contractor will have begun installation of the rebuilt motor and new equipment. As mentioned in the previous report, the contractor had originally estimated an April completion date, but the delay in materials delivery has pushed that schedule into May. Once FRM has completed the installation of pumps and associated equipment, Control Automation Design will finalize the repair and replacement of the City's electronic communications.
Please recall that Staff has filed a claim with the SCE contractor, and will continue to pursue reimbursement.
Therefore, staff recommends that City Council:
1) Approve by 4/5 vote the continuation of an emergency declared by the City Manager pursuant Resolution No. 12-6421, without soliciting competitive bids pursuant to California Public Contract Code Section 22050, for the replacement and installation of the stormwater pumps and equipment at the 23rd St. and Peck Ave. Stormwater Pump Station
POLICY ALTERNATIVES:
Do not find that there is a need to continue the replacement and installation of the Stormwater Pump Station pumps and equipment.
PROS:
General Funds would not be expended to complete the emergency repairs to the Stormwater Pump Station.
CONS:
Flooding of the intersection will continue during storm events, risking additional damage to public and private property.
PUBLIC OUTREACH/INTEREST:
Staff is continuing to maintain regular communication with the residents to keep them abreast of the project schedule and impacts during construction.
ENVIRONMENTAL REVIEW
The City reviewed the proposed project for compliance with the California Environmental Quality Act (CEQA) and determined that the project qualifies for a Class 1(b) categorical exemption pursuant to Section 15301, Existing Facilities of the State CEQA Guidelines. No environmental review is necessary.
LEGAL REVIEW
The City Attorney has reviewed this report and determined that no additional legal analysis is necessary.