Title: Resolution to Approve Change Order #2 to Miramontes Construction Company Inc. for $267,475 for Additional Sewer Line Rehabilitation Work and a Supplemental Appropriation of $60,000 from Sewer Fund Reserve (Public Works Director Katsouleas). ADOPT RESOLUTION AND APPROVE APPROPRIATION
Attachments: 1. Resolution No. 17-0048, 2. Budget and Expenditures Summary, 3. Location Map, 4. Contractor's Cost Proposal, 5. Plans (Web-Link Provided)
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Mark Danaj, City Manager

FROM:
Stephanie Katsouleas, Public Works Director
Prem Kumar, City Engineer

SUBJECT:Title
Resolution to Approve Change Order #2 to Miramontes Construction Company Inc. for $267,475 for Additional Sewer Line Rehabilitation Work and a Supplemental Appropriation of $60,000 from Sewer Fund Reserve (Public Works Director Katsouleas).
ADOPT RESOLUTION AND APPROVE APPROPRIATION
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council:

1. Authorize the City Manager to execute a Change Order with Miramontes Construction Company Inc. for $267,475 under the Sewer Main Rehabilitation Project Phase 2 contract to include additional sewer main replacement work on 13th Street (Attachments 1 and 4);

2. Appropriate $60,000 from the Sewer Fund Reserves for the additional sewer rehabilitation work.

3. Approve the plans for the 13th Street Sewer Main Replacement Project. (Attachment 5: Web-link provided)
Body
FISCAL IMPLICATIONS:
The Sewer Main Rehabilitation Project Phase 2 work has a remaining contract and contingency budget $237,938. An additional $60,000 must be appropriated from the Sewer Fund Reserve to cover the cost of the additional sewer rehabilitation work requested for the 13th Street sewer main and for additional inspection services and contingencies. The Budget and Expenditure summary report is provided in Attachment 2.

BACKGROUND:
On February 2, 2016, City Council awarded a $1,280,000 contract for the Sewer Main Rehabilitation Project Phase 2 construction project to Miramontes Construction Company Inc. and authorized an additional contingency of $128,000. The work included sewer main replacements at four locations, including 3rd Street, 4th Street, 7th Street and Ingleside Drive. The contractor recently completed that scope of work for a total of $1,170,062, which included one contract cha...