Title: Formally Accept the Live Oak Park Tennis Office Communication Project as Complete, and Authorize Filing of the Notice of Completion and Release of Retention in the Amount of $2,450 (Public Works Director Katsouleas). APPROVE
Attachments: 1. Live Oak Park Location Map
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Mark Danaj, City Manager

FROM:
Stephanie Katsouleas, Public Works Director
Sanford Taylor, Information Technology Director
Prem Kumar, City Engineer
Tim Birthisel, Project Manager

SUBJECT:Title
Formally Accept the Live Oak Park Tennis Office Communication Project as Complete, and Authorize Filing of the Notice of Completion and Release of Retention in the Amount of $2,450 (Public Works Director Katsouleas).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council:

1. Formally Accept the Live Oak Park Tennis Office Communication Project as Complete.
2. Authorize Filing of the Notice of Completion and Release of Retention in the Amount of $2,450.
Body
FISCAL IMPLICATIONS:
The construction work was completed for the contract award amount of $49,000. It was not necessary to utilize the construction contingency amount approved for the project.

BACKGROUND:
Live Oak Park Tennis Office currently does not have access to the City Network or a reliable internet connection. Approximately 15,000 reservations are made manually either through walk-in or via call-in, which leaves room for error. Approximately 45,000 participants play tennis annually at Live Oak Park. With a reliable connection to the internet, online tennis reservations will be available, creating an opportunity for better customer service as participants will have the opportunity to make a reservation from home and pay by credit card, a better system for auditing and increase revenues. On January 17, 2017, City Council authorized the City Manager to award a construction contract in the amount of $49,000 to Alfaro Communication Construction Inc.

DISCUSSION:
Construction started on February 2, 2017 and was completed on February 24, 2017. No change orders were issued during the course of the project. Consequently, it was not necessary to utiliz...