File #: RES 16-0080    Version: 1
Type: Public Hearing - SR w/Resolution Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 12/20/2016 Final action:
Title: Conduct Public Hearing to Consider Resolution No. 16-0080 Regarding a Coastal Development Permit to Install New Crash Rated Bollards and Replace Existing Bollards Along Both Sides of the Marvin Braude Bike Trail Adjacent to the Manhattan Beach Pier (Public Works Director Katsouleas). CONDUCT PUBLIC HEARING ADOPT
Attachments: 1. Resolution No. 16-0080, 2. Bollard Project Location Map, 3. Bollard Design Layout, 4. Pier Bollard Plans
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Mark Danaj, City Manager

FROM:
Stephanie Katsouleas, Public Works Director
Marisa Lundstedt, Community Development Director
Eric Haaland, Associate Planner
Ish Medrano, Engineering Technician II
Prem Kumar, City Engineer

SUBJECT:Title
Conduct Public Hearing to Consider Resolution No. 16-0080 Regarding a Coastal Development Permit to Install New Crash Rated Bollards and Replace Existing Bollards Along Both Sides of the Marvin Braude Bike Trail Adjacent to the Manhattan Beach Pier (Public Works Director Katsouleas).
CONDUCT PUBLIC HEARING ADOPT
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council Adopt Resolution No. 16-0080 approving a Coastal Development Permit for the Pier Bollard Project. Body

FISCAL IMPLICATIONS:
In the Fiscal Year 2014-15, $100,000 was budgeted in the Capital Improvement Program fund for the Pier Bollard Project. In May, 2015, staff purchased 16 crash rated, stainless steel bollards for $80,577.14. In June, 2016 staff retained SA Associates for $8,625.00 for engineering design services to prepare plans and specifications for installation of the new bollards and replacement of the existing concrete bollards. The remaining funds available for installation now total $10,798.00.

The estimated construction cost for installation of the pier bollards is $274,500. There is sufficient fund balance in the State Pier and Parking Lot Fund (Fund 522) for the project. The actual appropriation needed for the project will be requested at the time of construction contract award based on the lowest responsible bid received.


BACKGROUND:
On May 5, 2015, the City Council authorized the purchase of stainless steel bollards with steel pipe inserts to be installed adjacent to the Manhattan Beach Pier, effectively separating the Marvin Braude Trail from Manhattan Beach Blvd and the entrance to the pier...