Title: Consideration of a Resolution Approving Amendment No. 2 to the Professional Design Services Agreement with Geosyntec Consultants for $743,550 for the Manhattan Beach Dominguez Channel Stormwater Infiltration and TMDL Trash Capture Project for a Total Not-to-Exceed Amount of $1,130,419 and Reappropriating $676,681 in the Storm Drain Fund to the Project (Partially Budgeted) (Interim Public Works Director DeFrancesco). A) ADOPT RESOLUTION NO. 26-0024 B) REAPPROPRIATE FUNDS
Attachments: 1. Resolution No. 26-0024, 2. Amendment No. 2 - Geosyntec, 3. Agreement (and Amendment No.1 - Geosyntec, 4. Agreement - Clark Contracting Corp, 5. MB DC Infiltration Project Feasibility Study Summary Memo (2026-03-06)_Complete, 6. Budget Expenditure Summary Report_rev, 7. Location Map
Date Ver.Action ByActionResultAction DetailsDetailsVideo
No records to display.
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Talyn Mirzakhanian, City Manager

FROM:
Joe DeFrancesco, Interim Public Works Director
Gilbert Gamboa, City Engineer
Eddie Pech, Senior Civil Engineer

SUBJECT:Title
Consideration of a Resolution Approving Amendment No. 2 to the Professional Design Services Agreement with Geosyntec Consultants for $743,550 for the Manhattan Beach Dominguez Channel Stormwater Infiltration and TMDL Trash Capture Project for a Total Not-to-Exceed Amount of $1,130,419 and Reappropriating $676,681 in the Storm Drain Fund to the Project (Partially Budgeted) (Interim Public Works Director DeFrancesco).
A) ADOPT RESOLUTION NO. 26-0024
B) REAPPROPRIATE FUNDS
Body
_________________________________________________________

RECOMMENDATION:
Staff recommends that the City Council:
1. Consider Resolution No. 26-0024 approving Amendment No. 2 to the Professional Services Agreement (PSA) with Geosyntec Consultants, Inc. (Geosyntec) for additional design services for $743,550 for the Manhattan Beach Dominguez Channel Stormwater Infiltration Project for a Total Not-to-Exceed Amount of $1,130,419;
2. Authorize the City Manager, and/or his or her designee, to execute Amendment No. 2 to the PSA, and;
3. Reappropriate $676,681 in the Storm Drain Fund from the Annual Storm Drain Repairs Project to the Manhattan Beach Dominguez Channel TMDL Trash Capture Project.

FISCAL IMPLICATIONS:
The amendment to the PSA with Geosyntec is for $743,550 for additional design services. The Manhattan Beach Dominguez Channel Stormwater Infiltration Project budget consists of $450,000 within the Storm Drain Fund and $258,337 within the Measure W Fund. An additional appropriation of $676,681 is needed to fully fund the project. Sufficient funds of $676,681 are currently available for the project as a reappropriation from the available funds for the Annual Storm Drain Repairs program in the Storm Drain Fund. A Project Budget and Expenditures Summary is atta...