Second Amendment ($13,000) to the Professional Services Agreement with Psomas for Additional Design Services for the Sepulveda Boulevard and 2nd Street Water Main Replacement Project.
APPROVE
Line
_____________________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council authorize the City Manager to approve the Second Amendment to the Professional Engineering Services Agreement with Psomas for additional design services for the Sepulveda Boulevard and 2nd Street Water Main Replacement Project in the amount of $13,000.
Body
FISCAL IMPLICATIONS:
Funding for this project has been appropriated by the City Council in the amounts indicated in Attachment No.1.
BACKGROUND:
This project is part of the City's ongoing program to replace aging water mains within the City's water distribution system. This project provides for construction of replacement water mains and new fire hydrants along Sepulveda Boulevard from Manhattan Beach Boulevard to 2nd Street and along 2nd Street from the Larsson Street Pump Station to the 2nd Street Pump Station. In addition, new or replacement pipes crossing Sepulveda Boulevard would be constructed at 3rd, 9th, 10th, and 11th Streets.
The existing water mains on the west side of Sepulveda Boulevard are 70 to 80 years old. Replacing these mains and the main along 2nd Street will assure the longevity and dependability of the water system.
On April 3, 2012, the City Council awarded a professional engineering services agreement to Psomas for design services for the Sepulveda Boulevard and 2nd Street Water Main Replacement Project in the amount of $75,000, approved the First Amendment to the Agreement with Psomas in an amount not-to-exceed $5,000 for a...