Manhattan Beach Logo
File #: CON 15-0027    Version: 1
Type: Consent - SR w/Contract Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 5/19/2015 Final action:
Title: Approval of Plans and Specifications; Award Section 3 Concrete Repair Project to PK Construction, Inc. in the Amount of $237,050; Approve an Additional Appropriation in the Amount of $30,761; and Authorize the City Manager to Approve Additional Work in an Amount Not-to-Exceed $23,705 (10%) (Public Works Director Olmos). APPROVE; APPROPRIATE
Attachments: 1. Revenue and Expenditure Table, 2. Notices to Property Owners, 3. Project Area Map- Section 3, 4. Contract Agreement - Section 3 Concrete Repair
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Mark Danaj, City Manager

FROM:
Tony Olmos, Director of Public Works
Juan Price, Maintenance Superintendent

SUBJECT:Title
Approval of Plans and Specifications; Award Section 3 Concrete Repair Project to PK Construction, Inc. in the Amount of $237,050; Approve an Additional Appropriation in the Amount of $30,761; and Authorize the City Manager to Approve Additional Work in an Amount Not-to-Exceed $23,705 (10%) (Public Works Director Olmos).
APPROVE; APPROPRIATE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council:
1. Approve the Plans and Specifications of the Section 3 Concrete Repair Project,

2. Authorize the City Manager to execute a contract in the amount of $237,050 with PK Construction for the Section 3 Concrete Repair Project,

3. Approve Additional Appropriation in the amount of $30,761 from the Proposition 42 Gas Tax funded portion of the Capital Improvement Budget,

4. Authorize the City Manager to approve additional work in an amount not-to-exceed $23,705 (10%).
Body
FISCAL IMPLICATIONS:
Funds are available for this project in the approved Proposition 42 Gas Tax funded portion of the Capital Improvement Budget. Surplus funds from the 2013 Annual Slurry Seal project in the amount of $128,760, and an additional $101,232 are available from the 14/15 Annual Curb, Gutter and Ramp Project. An additional appropriation of $30,761 is being requested from the Proposition 42 Gas Tax funded portion of the Capital Improvement Budget to fully fund the current project.

BACKGROUND:
This project is part of the City's ongoing concrete repair and maintenance program. This annual program removes and replaces damaged or displaced concrete sidewalks, curbs, gutters and drive approaches in the City right-of-way to eliminate trip hazards and to mitigate gutter ponding. Installation o...