TO:
Honorable Mayor and Members of the City Council
THROUGH:
Mark Danaj, City Manager
FROM:
Tony Olmos, Director of Public Works
Juan Price, Maintenance Superintendent
SUBJECT:Title
Approval of Plans and Specifications and Award of Section 2 Concrete Repair and Miscellaneous Slurry Project to Nobest, Inc. in the amount of $1,119,790.80 (Public Works Director Olmos).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council:
a) Approve the Plans and Specifications of Section 2 Concrete Repair and Miscellaneous Slurry Project.
b) Authorize the City Manager to execute a contract in the amount of $1,119,790.80 with Nobest, Inc. for Section 2 Concrete Repair and Miscellaneous Slurry Project and,
c) Authorize the City Manager to approve additional work in an amount not-to-exceed $111,979 (10%).
Body
FISCAL IMPLICATIONS:
Sufficient funds are available for this project in the approved Proposition 42 Gas Tax funded portion of the Capital Improvement Budget and the Public Works Operating Budget (School Maintenance, Account 100-18-043-5101).
BACKGROUND:
This project is part of the City's ongoing concrete repair and maintenance program. This annual program removes and replaces damaged or displaced concrete sidewalks, curbs, gutters and drive approaches in the City right-of-way to eliminate trip hazards and to mitigate gutter ponding. Installation of ADA access ramps at select locations are also part of the program. Work under the program is performed through a competitively bid contract.
Concrete repairs (primarily curb, gutters, sidewalks and concrete drainage swales) are coordinated with established slurry seal maintenance districts. The goal is to provide a programmed approach to street maintenance in which street repairs, slurry sealing, sidewalk repairs, and traffic markings are completed within the same year and in the corresponding dist...
Click here for full text