TO:
Honorable Mayor and Members of the City Council
THROUGH:
Mark Danaj, City Manager
FROM:
Tony Olmos, Public Works Director
Prem Kumar, City Engineer
Gilbert Gamboa, Senior Civil Engineer
SUBJECT:Title
Discuss and Provide Direction for 7TH Street Walk Street Reconstruction (Public Works Director Olmos).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council discuss and provide direction for the 7th Street pedestrian walk street reconstruction.
FISCAL IMPLICATIONS:
Fiscal implications as outlined in this report will be dependent on City Council direction.
BACKGROUND:
The Sewer Main Rehabilitation Project was awarded by City Council on February 2, 2016 in the amount of $1,280,000. The City Council also authorized a not-to-exceed $128,000 contingency fund for potential additional work that could be authorized by the City Manager during construction. The scope of work entails replacement of over 2,300 linear feet of sanitary sewer pipe at the following four project street locations in the City's Sand Section:
1. 3rd Street - Ingleside Drive to Crest Drive
2. 4th Street - Ingleside Drive to Valley Drive
3. Ingleside Drive - 5th Street to 7th Street
4. 7th Street - Valley Drive to Crest Drive (pedestrian walk-street)
The sequence of work includes installation of sewer mains, connection of sewer laterals, and restoration of the trench and surface pavement. To date, the contractor has completed all work on Ingleside Drive. The contractor has also completed the sewer work on 7th Street and is awaiting direction from the City on surface pavement restoration work. The contractor is currently working to complete the sewer work on 4th Street and then on 3rd Street. Based on the progress made so far, the contractor anticipates completing all work sometime in mid-August 2016.
Shortly after the award of construction contract, ...
Click here for full text