TO:
Honorable Mayor and Members of the City Council
THROUGH:
Talyn Mirzakhanian, City Manager
FROM:
Ramzi Awwad, Public Works Director
Gilbert Gamboa, City Engineer
Bianca Cardenas, Senior Civil Engineer
SUBJECT:Title
Consideration of a Resolution Ratifying a Construction Agreement with Applied Restoration, Inc. In the Amount of $103,826.82, Approving Plans and Specifications, and Accepting the Work as Complete for the Emergency Shoring at the Lot 3 Parking Structure Project (Budgeted) (Public Works Director Awwad).
A) ADOPT RESOLUTION NO. 26-0084
B) ACCEPT AS COMPLETE
Body
_________________________________________________________
RECOMMENDATION:
Staff recommends that the City Council:
1. Adopt Resolution No. 26-0084:
a) Ratifying the approval of plans and specifications for the Emergency Shoring at the Lot 3 Parking Structure Project;
b) Ratifying a construction agreement with Applied Restoration, Inc. in the amount of $103,826.82 for the Emergency Shoring at the Lot 3 Parking Structure; and
c) Authorizing the City Manager to execute the Agreement;
2. Formally accept as complete the Applied Restoration, Inc. construction contract for the Emergency Shoring at the Lot 3 Parking Structure;
3. Authorize the filing of the Notice of Completion with the County Recorder; and
4. Release the retention of $5,191.34.
FISCAL IMPLICATIONS:
Sufficient funds of $126,072 are currently available in the Parking Lot 3 Redevelopment Project for emergency shoring toward demolition within the Parking Fund. After the payment to Applied Restoration, the remaining project balance is $22,246.16. A Project Budget and Expenditures Summary is attached.
BACKGROUND:
The Lot 3 Parking Structure was a City-owned facility located at the southwest corner of Morningside Drive and 12th Street in Downtown Manhattan Beach. Built in 1971, this three-story structure provided 144 parking spaces, which were vital for visitors and businesses in the Downtown area. In June 2024, a series of...