TO:
Honorable Mayor and Members of the City Council
THROUGH:
David N. Carmany, City Manager
FROM:
Jim Arndt, Public Works Director
Edward Kao, Senior Civil Engineer
SUBJECT:Title
Progress Payment No. 5 in the amount of $180,455.95 to Vido Samarzich, Inc. for the Fiscal Year 2012-13 Water Main Replacement and Fire Hydrant Installation Project (Area 1, Hill Section; 8th, 9th, 10th, 11th and John Streets; and Highview, Pacific and Poinsettia Avenues).
APPROVE
Line
_____________________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council approve Progress Payment No. 5 in the amount of $180,455.95 to Vido Samarzich, Inc. for the Fiscal Year 2012-13 Water Main Replacement and Fire Hydrant Installation Project (Area1) [95% ($171,433.15) would be released immediately and 5% ($9,022.80) would be retained and released after project completion].
Body
FISCAL IMPLICATIONS:
Water Enterprise Funds in the amount of $1,200,000 were appropriated by City Council through the Fiscal Year 2011-12 and 2012-13 Capital Improvement Plans. An additional appropriation in the amount of $320,000 was approved by City Council on August 7, 2012, bringing total project appropriations to $1,520,000. Anticipated expenditures total to $1,390,490 which will leave an anticipated balance of $129,510 upon completion of the project. Please see Attachment 1, Table 1 for budget, anticipated expenditure and progress payment details in tabular format.
BACKGROUND:
This project is part of the City's annual water main replacement program which replaces old and/or undersized water mains. These main replacements will reduce the risk of main breaks and will enhance fire suppression flows.
As part of the Fiscal Year 2012-2013 Water Main Replacement and Fire Hydrant Installation (Area 1) Project, new 6" and 8" diameter ductile iron pipes are being installed to replace 6,350 lineal feet of existing wa...