File #: 23-0228    Version: 1
Type: Consent - Staff Report Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 7/5/2023 Final action: 7/5/2023
Title: Consideration of a Resolution Awarding a Construction Agreement to Sprinturf, LLC for the Marine Avenue Park Synthetic Field Turf Replacement Project for $541,350 Including Contingency; and Determination Pursuant to the California Environmental Quality Act (CEQA) that this Activity is Categorically Exempt Pursuant to the State CEQA Guidelines (Public Works Director Lee). ADOPT RESOLUTION NO. 23-0088
Attachments: 1. Resolution No. 23-0088, 2. Agreement – Sprinturf, LLC., 3. Bid Proposal, 4. Plans and Specifications, 5. Budget and Expenditures Summary, 6. Location Map
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Bruce Moe, City Manager

FROM:
Erick Lee, Public Works Director
Katherine Doherty, City Engineer
Gilbert Gamboa, Principal Civil Engineer

SUBJECT:Title
Consideration of a Resolution Awarding a Construction Agreement to Sprinturf, LLC for the Marine Avenue Park Synthetic Field Turf Replacement Project for $541,350 Including Contingency; and Determination Pursuant to the California Environmental Quality Act (CEQA) that this Activity is Categorically Exempt Pursuant to the State CEQA Guidelines (Public Works Director Lee).
ADOPT RESOLUTION NO. 23-0088
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council:

1. Adopt Resolution No. 23-0088:

a. Awarding a construction contract to Sprinturf, LLC for the Marine Avenue Park Synthetic Field Turf Replacement Project for $491,350 and authorizing the City Manager to execute the agreement; and

b. Approve reallocation funding in the amount of $200,000 from the Deferred Park Maintenance Program in the CIP Fund to the Project.

c. Authorizing the City Manager and/or his or her designee to approve an extra work contingency up to $50,000; and

d. Approving the Final Plans and Specifications for the Project.

2. Determine that pursuant to CEQA, the activity is Categorically Exempt pursuant to State CEQA Guidelines.


FISCAL IMPLICATIONS:
The Marine Ave Park Synthetic Field Turf Replacement Project was approved as part of the Fiscal Year (FY) 2023-2024 Capital Improvement Plan with a budget of $400,000 along with matching revenues within the Capital Improvement Program (CIP) Fund. After the receipt of bids for construction, staff now estimates the total cost for the Marine Ave Park Synthetic Field Turf Replacement Project to be $600,000 as outlined in the attached Budget and Expenditure Summary. If approved, sufficient funds to cover the projected shortfall are available from a reallocat...

Click here for full text