TO:
Honorable Mayor and Members of the City Council
THROUGH:
Bruce Moe, City Manager
FROM:
Erick Lee, Public Works Director
Katherine Doherty, City Engineer
Marzena Laskowska, Senior Civil Engineer
SUBJECT:Title
Consideration of a Resolution Approving the Professional Design Services Agreement with PACE Inc. for Final Design Services for the Poinsettia Ave Sewer Lift Station Improvement Project at a Cost Not-to-Exceed $450,215 and Making a Determination of Exemption Pursuant to Sections 15302 Class 2 of the State CEQA Guidelines (Public Works Director Lee).
ADOPT RESOLUTION NO. 23-0140
Body
_________________________________________________________
RECOMMENDATION:
Staff recommends that City Council:
1. Adopt Resolution No. 23-0140 approving the professional services agreement with Pacific Advanced Civil Engineering, Inc. (PACE) for final design services and preparation of construction bid documents for the Poinsettia Avenue Sewer Lift Station Improvement Project at a Cost Not-to-Exceed $450,215; and
2. Make a Determination of Exemption Pursuant to Sections 15302 Class 2 of the State CEQA Guidelines for Poinsettia Avenue Sewer Lift Station Improvement Project.
FISCAL IMPLICATIONS:
The Poinsettia Avenue Sewer Lift Station Improvement Project is included in the current Capital Improvement Program (CIP) with a total project budget of $3.3 million within Wastewater Fund. This agreement will cover the final design engineering necessary to construct the Poinsettia Avenue sewer lift station. There are sufficient funds available to complete the final design contract for $450,215, as shown in the Budget and Expenditures summary table (attachment). There are no additional fiscal implications at this time.
BACKGROUND:
The City currently operates and maintains an extensive sanitary sewer system. The City's existing wastewater collection system is comprised of a network of gravity sewer pipelines, lift (pump) stations, and force mains. The gravity system consists o...