Manhattan Beach Logo
File #: CON 15-0015    Version: 1
Type: Consent - SR w/Contract Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 4/7/2015 Final action:
Title: Approve Consultant Agreement with Nonzero\Architecture for Architectural and Engineering Design Services for the Rehabilitation of the Manhattan Beach Pier, Pier Roundhouse and Pier Comfort Station in the Amount of $155,400 and Authorize City Manager to Execute Consultant Agreement (Public Works Director Olmos). APPROVE
Attachments: 1. Faithful+ Gould FSA Report Pier Complex, 2. Professional Services Agreement
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Mark Danaj, City Manager

FROM:
Tony Olmos, Public Works Director
Juan Price, Maintenance Superintendent
Karen Domerchie, Senior Management Analyst

SUBJECT:Title
Approve Consultant Agreement with Nonzero\Architecture for Architectural and Engineering Design Services for the Rehabilitation of the Manhattan Beach Pier, Pier Roundhouse and Pier Comfort Station in the Amount of $155,400 and Authorize City Manager to Execute Consultant Agreement (Public Works Director Olmos).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council:
1) Approve Consultant Agreement with Nonzero\Architecture for architectural and engineering design services for the rehabilitation of the Manhattan Beach Pier, Pier Roundhouse and Pier Comfort Station in the amount of $155,400.
2) Authorize City Manager to execute Consultant Agreement.
3) Approve a Design Contingency in the amount of $31,800 (20%).
Body
FISCAL IMPLICATIONS:
City Council appropriated sufficient State Pier and Parking Funds for this project as part of the fiscal year 2014-2015 Capital Improvement Plan.

BACKGROUND:
The Pier complex includes the Pier, adjoining structures and the four parking lots west of Ocean Avenue. The Manhattan Beach Pier was originally developed circa 1917. The Pier Roundhouse was constructed in 1921, rebuilt in 1992 and further renovated in 2002. The Comfort Station was also rehabilitated in 2002 in conjunction with the Roundhouse. In 1988, the City entered into an operating agreement with the State of California in which the City assumed maintenance responsibilities for the Pier. Revenues generated through Pier parking operations fund all maintenance and operations of the Pier complex. Located at the base of the Pier, the County of Los Angeles Lifeguard Station is operated by the County of Los Angeles through a separate ag...

Click here for full text