TO:
Honorable Mayor and Members of the City Council
THROUGH:
Talyn Mirzakhanian, City Manager
FROM:
Erick Lee, Public Works Director
Katherine Doherty, City Engineer
Gilbert Gamboa, Principal Civil Engineer
SUBJECT:Title
Consideration of Resolutions Making a Determination that the Manhattan Beach Advanced Traffic Signal (MBATS) System Project Qualifies for a Categorical Exemption Pursuant to Section 15301 Class 1 (c) of the State CEQA Guidelines; Approving the Plans and Specifications; Awarding a Construction Agreement to Crosstown Electrical & Data, Inc. for $15,028,763, Including Contingency; and Approving the Professional Services Agreement with Ardurra Group, Inc. for $1,111,741 for Construction Management and Inspection Services (No Budget Impact) (Public Works Director Lee).
A) ADOPT RESOLUTION NOS. 25-0032 AND 25-0033
B) MAKE A DETERMINATION OF EXEMPTION PURSUANT TO CEQA
Body
_________________________________________________________
RECOMMENDATION:
Staff recommends that the City Council:
1. Adopt Resolution No. 25-0032:
a. Making a Determination of Exemption Pursuant to Sections 15301 Class 1 of the State CEQA Guidelines Section;
b. Approving the final plans and specifications for the Manhattan Beach Advanced Traffic Signal System Project (MBATS System Project);
c. Awarding a Construction Agreement to Crosstown Electrical & Data, Inc. for the MBATS System Project for $13,662,512; and
d. Authorizing the City Manager to execute the agreement and authorizing the City Manager and/or his or her designee to approve extra work contingency up to $1,366,251.
2. Adopt Resolution No. 25-0033:
a. Approving a Professional Services Agreement with Ardurra Group, Inc. in the amount of $1,111,741 for Construction Management and Inspection Services for the MBATS System Project; and
b. Authorizing the City Manager and/or his or her designee to execute the agreement.
FISCAL IMPLICATIONS:
Sufficient funds of $17,713,000 are currently available for the MBATS System P...