TO:
Honorable Mayor and Members of the City Council
THROUGH:
Talyn Mirzakhanian, City Manager
FROM:
Ramzi Awwad, Public Works Director
Gilbert Gamboa, City Engineer
Justin Murray, Engineering Technician II
SUBJECT:Title
Update for Underground Utility Assessment Districts 19-12 and 19-14 (No Budget Impact) (Public Works Director Awwad).
(Estimated Time: 30 Mins.)
RECEIVE AND FILE
Body
_________________________________________________________
RECOMMENDATION:
Staff recommends that the City Council receive and file the update on Underground Utility Assessment Districts 19-12 and 19-14 (Districts 12 and 14).
EXECUTIVE SUMMARY:
Underground Utility Assessment Districts 12 and 14 have advanced substantially since the City Council’s October 2025 update. Most private properties are now either connected to underground electrical service or have completed the City inspection approval process and are awaiting final connection by Southern California Edison (SCE). Significant progress has also been made on underground telecommunications connections and the removal of overhead facilities.
As of November 2026, 356 of the 460 properties are converted/connected to underground electrical service, 55 are released/approved by the City for SCE connection, 46 are not released/approved for SCE connection because additional private property work or coordination remains, and three are currently identified for City-managed conversion/connection.
Since the October 2025 City Council update, the number of properties connected to underground electrical service has increased by 88, while the number of properties not approved for SCE connection decreased from 109 to 46. Overall, the percentage of properties either connected to underground service or approved by the City for SCE connection has increased from approximately 74 percent to 89 percent. City staff continues to work directly with private electrical contractors and SCE to resolve outstanding issues, advance inspection releases/a...
Click here for full text