File #: CON 15-0023    Version: 1
Type: Consent - SR w/Contract Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 5/19/2015 Final action:
Title: Approval of Plans and Specifications for the Block 35 Reservoir Pump Station Discharge Line Project and the Marine Avenue and Herrin Avenue Water Main Connection Project, Award a Construction Contract to Miramontes Construction Company, Inc. in the Amount of $211,400. (Public Works Director Olmos). APPROVE
Attachments: 1. Construction Contract (Miramontes Construction Company, Inc.)
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Mark Danaj, City Manager

FROM:
Tony Olmos, Director of Public Works
Joe Parco, City Engineer
Raul Saenz, Utilities Manager

SUBJECT:Title
Approval of Plans and Specifications for the Block 35 Reservoir Pump Station Discharge Line Project and the Marine Avenue and Herrin Avenue Water Main Connection Project, Award a Construction Contract to Miramontes Construction Company, Inc. in the Amount of $211,400. (Public Works Director Olmos).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council:
1. Approve plans and specifications for the Block 35 Reservoir Pump Station Discharge Line Project and the Marine Avenue and Herrin Avenue Water Main Connection Project,

2. Award a construction contract to Miramontes Construction in the amount of $211,400, and

3. Authorize the City Manager to approve additional work, if necessary, in an amount not-exceed $21,140 (10% of bid) for the Block 35 Reservoir Pump Station Discharge Line Project and the Marine Avenue and Herrin Avenue Water Main Connection Project.

FISCAL IMPLICATIONS:
There are sufficient previously approved funds in the FY 2014/2015 Capital Improvement Program for this specific project.

BACKGROUND:
The Block 35 Reservoir Pump Station Discharge Line Project will replace a 25 foot long, 20 inch diameter section of water discharge main beginning at the reservoir's point of discharge inside the booster station to a point of connection at the 20 inch diameter distribution system transmission line. The discharge main is comprised of two access values, flow meter, three isolation valves and a 20 inch tee.

The Herrin/Marine Project involves installation of new section of 10 inch diameter water distribution main that will connect the 16 inch Peck Reservoir transmission main at Herrin Avenue to a 10 inch water main at Marine Avenue. This...