Title: Consideration of an Update on the Lot 3 Parking Structure, Alternative Parking Solutions, and Business Impacts; and Adoption of a Resolution Directing and Delegating Authority to the City Manager Authority to Take Emergency Action to Secure, Demolish and Replace (Public Works Director Lee and Acting Community Development Director Heise). (Estimated Time: 1 Hr.) A) DISCUSS AND PROVIDE DIRECTION B) DETERMINE THAT PROJECT IS EXEMPT UNDER THE CALIFORNIA ENVIRONMENTAL QUALITY ACT C) ADOPT RESOLUTION NO. 24-0105
Attachments: 1. Location Map, 2. Resolution No. 24-0105, 3. Resolution No. 12-6422, 4. PowerPoint Presentation
TO:
Honorable Mayor and Members of the City Council

THROUGH:
Talyn Mirzakhanian, Acting City Manager

FROM:
Erick Lee, Public Works Director
Ryan Heise, Acting Community Development Director
Onyx Jones, Interim Finance Director
Katherine Doherty, City Engineer
Alexandria Latragna, Communications and Civic Engagement Manager

SUBJECT:Title
Consideration of an Update on the Lot 3 Parking Structure, Alternative Parking Solutions, and Business Impacts; and Adoption of a Resolution Directing and Delegating Authority to the City Manager Authority to Take Emergency Action to Secure, Demolish and Replace (Public Works Director Lee and Acting Community Development Director Heise).
(Estimated Time: 1 Hr.)
A) DISCUSS AND PROVIDE DIRECTION
B) DETERMINE THAT PROJECT IS EXEMPT UNDER THE CALIFORNIA ENVIRONMENTAL QUALITY ACT
C) ADOPT RESOLUTION NO. 24-0105
Line
_________________________________________________________

RECOMMENDATION:
Staff recommends that the City Council:

A. Discuss and provide direction regarding the demolition of the Lot 3 Parking Structure (Lot 3) and replacement of parking at the site, alternative parking solutions, and consider the impacts to businesses; and
B. Adopt Resolution No. 24-0105.

FISCAL IMPLICATIONS:
The closure and demolition of Lot 3 will have the following fiscal implications:

- Demolition and Replacement Costs: The estimated cost for demolition and replacement of Lot 3 with an at-grade parking lot is projected to be up to $3,000,000. Pursuant to Manhattan Beach Municipal Section 3.08.060.A.6.c, the emergency demolition and replacement phase may be done through an emergency contract and may be partially funded with funds available in the Parking Fund. The emergency contract, associated costs and any necessary budget appropriations will be brought to City Council at a future date for ratification. In addition to the appropriation from the Parking Fund, it is anticipated that another funding source will need to be identified.
- Loss ...