Consideration of Resolutions Approving Change Order No. 2 to the Construction Agreement with Clarke Contracting Corporation for Additional Work in the Amount of $626,468 and Approving Amendment No. 2 to the Professional Services Agreement with CWE Corporation for Additional Design and Construction Support Services for $123,754 for the Santa Monica Bay Stormwater Total Maximum Daily Load Trash Treatment Project; and Reappropriating $479,121 in the Storm Drain Fund for the Santa Monica Bay Stormwater Total Maximum Daily Load Trash Treatment Project (No Budget Impact) (Interim Public Works Director Semaan).
A) ADOPT RESOLUTIONS NOS. 25-0107 AND 25-0108
B) APPROVE REAPPROPRIATION OF FUNDS
Body
_________________________________________________________
RECOMMENDATION:
Staff recommends that City Council:
A. Adopt Resolution No. 25-0107, approving Contract Change Order No. 2 (CCO2) with Clarke Contracting Corporation (Clarke) for additional work in the amount of $626,468 to include the Dominguez Channel Trash Total Maximum Daily Load (Dominguez Channel TMDL) Project and authorizing the City Manager, and/or his or her designee, to execute the CCO2; and
B. Adopt Resolution No. 25-0108, approving Amendment No. 2 to the Professional Services Agreement with CWE Corporation (CWE) for additional design and construction support services in the amount of $123,754 for the Santa Monica Bay Stormwater Total Maximum Daily Load Trash Treatment Project (SM Bay TMDL Project); and authorizing the City Manager, and/or his or her designee, to execute Amendment No. 2.
C. Approve the reappropriation of $479,121 from the Annual Storm Drain Capital BMP Project to the SM Bay TMDL Project within the Storm Drain Fund.
FISCAL IMPLICATIONS:
The original construc...