Skip to main content
Manhattan Beach Logo
File #: CON 13-0035    Version:
Type: Consent - SR w/Contract Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 9/17/2013 Final action: 9/17/2013
Title: Contract for Construction Inspection Services ($43,720) with Willdan Engineering for the Street Resurfacing Project for Ardmore Avenue, Valley Drive and 11th Place. APPROVE
Sponsors: Vince Mastrosimone
Attachments: 1. Funding and Anticipated Expenditures, 2. Location Map of Street Resurfacing Project for Ardmore Ave, Valley Dr and 11th Pl, 3. Agreement for Professional Services - Inspection (Willdan Engineering)
TO:
Honorable Mayor and Members of the City Council

THROUGH:
David N. Carmany, City Manager

FROM:
Tony Olmos, Public Works Director
Gilbert Gamboa, Senior Civil Engineer

SUBJECT:Title
Contract for Construction Inspection Services ($43,720) with Willdan Engineering for the Street Resurfacing Project for Ardmore Avenue, Valley Drive and 11th Place.
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
It is recommended that the City Council pass a motion to:

1. Authorize the City Manager to award a contract in the amount of $43,720 to Willdan Engineering for the inspection of the Street Resurfacing Project for Ardmore Avenue, Valley Drive and 11th Place;
2. Authorize the City Manager to approve additional inspection work, if necessary, in an amount not-to-exceed $4,372 (10%).
Body
FISCAL IMPLICATIONS:
Gas Tax funds in the amount of $582,696 have been appropriated by City Council for this project through the Fiscal Year 2011-2012 Capital Improvement budget. In addition, this project also includes Metropolitan Transportation Authority (MTA) STP-L funds in the amount of $117,304. The 2012-2013 Capital Improvement Program has added an additional $200,000 in Gas Tax funds to the project, bringing the total to $900,000. Total expenditures are anticipated to be $850,514. A summary of budget appropriations and anticipated expenditures is provided in Attachment 1.

BACKGROUND:
The existing pavement on Ardmore Avenue, Valley Drive and 11th Place is deteriorated and rehabilitation is required within the project limits as shown in Attachment 2. The project will cold mill and overlay the asphalt pavement surface and replace displaced curbs, gutters and sidewalk along Ardmore Avenue and Valley Drive. New concrete pavement will be constructed on 11th Place. Ponding occurs near Manhattan Beach Boulevard after rain storms and pavement deterioration is escalated due to localized nuisance water...