Title: Consideration of a Resolution Ordering Plans, Specifications, Cost Estimates, and Engineer's Report for Annual Street Lighting and Landscaping Assessments (No Budget Impact) (Acting Finance Director Bretthauer). ADOPT RESOLUTION NO. 25-0031
Attachments: 1. Resolution No 25-0031
Date Ver.Action ByActionResultAction DetailsDetailsVideo
No records to display.

TO:

Honorable Mayor and Members of the City Council

 

THROUGH:

Talyn Mirzakhanian, City Manager

 

FROM:

Libby Bretthauer, Acting Finance Director

Julie Bondarchuk, Financial Controller

                     

SUBJECT:Title

Consideration of a Resolution Ordering Plans, Specifications, Cost Estimates, and Engineer’s Report for Annual Street Lighting and Landscaping Assessments (No Budget Impact) (Acting Finance Director Bretthauer).

ADOPT RESOLUTION NO. 25-0031

Body

_____________________________________________________________________

RECOMMENDATION:

Staff recommends that the City Council adopt Resolution No. 25-0031 ordering the preparation of plans, specifications, cost estimates, and the engineer’s report for the annual renewal of the Landscaping and Lighting District for Fiscal Year (FY) 2025-2026, pursuant to the Landscaping and Lighting Act of 1972.

 

FISCAL IMPLICATIONS:

Sufficient funds are budgeted in the Public Works department for the assessment engineering cost of $8,000 for the Street Landscaping and Lighting District.

It is important to note that assessments have been fixed since 1996 with most single-family residences paying $17.03 per year. Costs, however, have continued to rise (notably electricity and gas) and exceed the revenue generated by the assessments. As a result, the Street Lighting and Landscape Fund balance has been depleted and the General Fund continues to subsidize the fund. The preliminary estimate for the subsidy in the upcoming FY 2025-2026 is $304,922. A Proposition 218 vote would be required to raise the assessments. 

 

BACKGROUND:
The City provides for the operations and maintenance of street lighting and the Downtown streetscape via the Street Lighting and Landscaping Assessment District (District). The District, which was formed pursuant to the Landscaping and Lighting Act of 1972, is comprised of separate street lighting districts for the majority of the City, and the lighting and landscaping services provided for Downtown.

 

DISCUSSION:

The District must be renewed annually through a series of City Council resolutions, culminating with a public hearing. The public hearing and adoption of a final resolution are scheduled for the City Council meeting of June 3, 2025.

In order to renew the districts, an assessment engineer must review and develop the benefit assessments for each parcel. Those assessments are based on the proposed budget for the upcoming fiscal year commencing July 1, subject to the constraints of Proposition 218.  For FY 2025-2026, the preliminary assessment is comprised of $377,468 from private property owners and a General Fund contribution of $13,517 for City property located in the Streetscape zone, for a total assessment of $390,985.  Since total assessments ($390,985) are the only budgeted resources for FY 2025-2026, the projected expenditures of $695,907 for all zones will result in a shortfall of $304,922 for all zones. The 2025-2026 fiscal year opening balance will not have available funds, requiring a General Fund subsidy to match the shortfall.

 

The first step in this annual process is for the City Council to pass a Resolution of Initiation on April 1, 2025, which authorizes the preparation of an engineer’s report on the District. During the May 6, 2025, City Council meeting, the engineer’s report will be submitted, along with a Resolution of Intention, which authorizes proceedings for the annual levy and collection of assessments. Finally, on June 3, 2025, the public hearing will be held. At that time, City Council will be asked to adopt a resolution providing for the levy and collection of street lighting assessments for FY 2025-2026.

 

PUBLIC OUTREACH:
After analysis, staff determined that public outreach was not required for this issue.

 

ENVIRONMENTAL REVIEW:
The City has reviewed the proposed activity for compliance with the California Environmental Quality Act (CEQA) and has determined that the activity is not a “Project” as defined under Section 15378 of the State CEQA Guidelines; therefore, pursuant to Section 15060(c)(3) of the State CEQA Guidelines the activity is not subject to CEQA.  Thus, no environmental review is necessary.

LEGAL REVIEW:
The City Attorney has reviewed this report and determined that no additional legal analysis is necessary.

 

ATTACHMENT:

1. Resolution No. 25-0031