File #: 14-0414    Version: 1
Type: Consent - Staff Report Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 10/21/2014 Final action:
Title: Final Payment in the Net Amount of $26,584.33 to Asphalt Fabric & Engineering, Inc.; Formally Accept the Marine Avenue Park Synthetic Turf Installation Project as Complete; and Authorize Filing of the Appropriate Notice of Completion and Release Retention in the Amount of $19,949.65 (Public Works Director Olmos). APPROVE
Attachments: 1. Budget and Expenditure Breakdown
TO:
Honorable Mayor and Members of the City Council
 
THROUGH:
Mark Danaj, City Manager
 
FROM:
Tony Olmos, Public Works Director
Joe Parco, City Engineer
Ish Medrano, Engineering Technician II
      
SUBJECT:Title
Final Payment in the Net Amount of $26,584.33 to Asphalt Fabric & Engineering, Inc.; Formally Accept the Marine Avenue Park Synthetic Turf Installation Project as Complete; and Authorize Filing of the Appropriate Notice of Completion and Release Retention in the Amount of $19,949.65 (Public Works Director Olmos).
APPROVE
Line
_________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that City Council authorize the City Manager to:
 
1.      Approve the issuance of a final payment in the net amount of $26,584.33 to   Asphalt Fabric & Engineering, Inc. for the Marine Avenue Park Synthetic Turf Installation Project;
 
2.      Formally accept the Marine Avenue Park Synthetic Turf Installation Project as complete; and
 
3.      Authorize filing of the appropriate Notice of Completion and the release of retention in the amount of $19,949.65.
Body
FISCAL IMPLICATIONS:
Capital Improvement Program funds in the amount of $273,076 have been appropriated by City Council in addition to a private donation of $845,000 for a total of $1,118,076 for this project.
 
BACKGROUND:
On November 6, 2012 the City Council approved a Memorandum of Understanding with the American Youth Soccer Organization (AYSO) for the construction of an artificial turf field at Marine Avenue Park.  The project was a partnership between the City of Manhattan Beach and AYSO.  City contributed $236,076 and AYSO along with other private donators contributed $845,000.
 
On June 20, 2013 the City Council awarded a construction contract to Asphalt Fabric & Engineering, Inc. for $737,496.  Since the construction contract came in under the engineer's estimate, City Council approved additional expenditures towards the project (Attachment 1).
 
DISCUSSION:
Construction of the synthetic turf field started on May 9, 2013 and became operational in September 2013 just prior to the 2013 soccer season, with the exception of two items.  The final two items were the construction of a concrete block shed and a steel shade structure that have now been completed.
 
CONCLUSION:
The Contractor has completed all contract work and is requesting formal acceptance of the work and final payment in the amount of $26,584.33. The retention in the amount of $19,949.65 would be released upon the expiration of 35 days after recordation of the Notice of Completion with the County Recorder. All work inspected by the Public Works Department has been found to be in conformance with the plans and specifications.
 
 
Attachment:
1. Budget and Expenditure Breakdown