TO:
Honorable Mayor and Members of the City Council
THROUGH:
Talyn Mirzakhanian, City Manager
FROM:
Ramzi Awwad, Public Works Director
Gilbert Gamboa, City Engineer
Marzena Laskowska, Principal Civil Engineer
SUBJECT:Title
Consideration of a Resolution Approving the Professional Services Agreement with Brookwood Group for $3,290,000 for Project Management, Construction Management, and Inspection Services for the Senior and Scout House Community Center Project (Budgeted) (Public Works Director Awwad).
ADOPT RESOLUTION NO. 26-0123
Body
_________________________________________________________
RECOMMENDATION:
Staff recommends that the City Council Adopt Resolution No. 26-0123:
1. Approving a professional services agreement with Brookwood Group, LLC in the amount of $3,290,000 for project management, construction management, and inspection services for the Senior and Scout Community Center Project; and
2. Authorizing the City Manager and/or his or her designee to execute the agreement.
FISCAL IMPLICATIONS:
Sufficient funds of $3,290,000 are currently available in the CIP Fund for the agreement with Brookwood Group, LLC for Project Management, Construction Management, and Inspection Services for the Senior and Scout Community Center Project. A Project Budget and Expenditures Summary is attached.
BACKGROUND:
The City operates and maintains the Scout House, located at 1617 North Valley Drive, adjacent to the Joslyn Community Center. Scouting families and volunteers built the original Scout House in 1952. It is an approximately 2,500-square-foot, single-story building on City-owned property that has served Scout troops and community seniors for nearly seven decades. The Scout House has provided many treasured memories over the years, from Scout meetings and service projects to ping-pong and art classes for seniors. It hosts more than 550 gatherings each year.
In 2013, the Friends of the Senior and Scout Community Center (Friends) was formed, having desired for several years to construct a new facility. The Friends hired Tomaro Design Group (Tomaro Group) to provide architectural and engineering services related to the Scout House.
In February 2014, the City, Friends, and the Manhattan Beach Property Owners Association (MBPOA) entered into a Memorandum of Understanding (MOU) that developed a path to replace the Scout House. Shortly thereafter, the Friends began fundraising for the new center.
On October 2, 2018, staff presented the City Council with information on financing opportunities pursuant to constructing a new facility (the Senior and Scout Community Center), and Friends presented updated budget projections and schematics for the building. At that meeting, after reviewing various funding opportunities, the City’s infrastructure budget, and the variety of projects already identified in the Five-Year Capital Improvement Program (CIP), the City Council allocated $1 million toward the construction of a new Senior and Scout Community Center.
On May 17, 2022, staff presented the City Council with an updated MOU between the City and Friends. The updated MOU stated that Friends was committing to funding at least $2,290,000 and the City was funding up to $2,899,540 to pay for the new Senior and Scout Community Center. Additionally, the City Council approved a contribution agreement with the MBPOA for their donation of $800,000 for the new Senior and Scout Community Center.
On March 7, 2023, the City Council allocated an additional $1,691,548 toward the new Senior and Scout Community Center. This brought the City’s contribution to a total of $4,591,088.
On August 1, 2023, the City Council approved a contribution agreement with Beach Cities Health District (BCHD) for their $150,000 contribution towards the new Senior and Scout Community Center.
On August 23, 2023, the Planning Commission approved the Use Permit and Coastal Development Permit to demolish the existing Scout House to accommodate the construction of a new Senior and Scout Community Center and made a determination that the new Senior and Scout Community Center project is exempt under the California Environmental Quality Act (CEQA). This information was conveyed to the City Council on September 5, 2023, as an information-only staff report.
On April 16, 2024, City Council approved a request from Sandpipers for the dedicated use of a room at a discounted rate at the new Senior and Scout Community Center for a ten-year term, in exchange for a $50,000 donation to the project.
On June 2, 2026, during adoption of the Five-Year CIP for Fiscal Year 2026-2027 through Fiscal Year 2030-2031; the City Council re-approved CIP funds in the total amount of $4,700,000 for the Senior and Scout Community Center Project (Project) and directed that the remaining amount needed, estimated to be approximately $10 million, be bonded.Starting on October 2, 2025, Tomaro Group, which had since been hired by Friends to prepare architectural and engineering plans for the new Senior and Scout Community Center Project, began submitting plans and revisions in response to comments from the Building and Safety Division. The plans were approved on October 21, 2026, by the Building and Safety Division.
DISCUSSION:
The Senior and Scout Community Center Project involves the demolition of the existing single-story building along with certain trees, and construction of a new approximately 6,700-square-foot two-story building.
The new community center will provide a larger central meeting space with breakout rooms, multiple rooms for expanded programming, a courtyard to enjoy an outdoor fire pit with an amphitheater, art and maker space, a dedicated senior lounge, a commercial kitchen for events and demonstrations, regular user group storage spaces, historical and award display cases, central air conditioning and heating, technology upgrades including Wi-Fi and computers, and new furnishings. Attached is an exhibit of the building layout.
Project Management, Construction Management, and Inspection Services
Approval of the building plans completed the design phase of the Project; however, additional professional services are needed during the remaining phases of the project to ensure a successful outcome. These services are described below:
• Coordination with the Architect/Engineer, which includes coordination of the architect/engineer on site visits; reviews of certain construction contractor submittals for conformance with plans and specifications; responses to requests for design clarifications from the construction contractor; and design revisions necessitated by unknown field conditions.
• Project Management and Construction Management, which includes activities such as management of the scope, schedule, and budget during construction; quality assurance reviews of all construction documents to minimize the risk of construction change orders due to errors, omissions, vague, or conflicting information; constructability reviews to assure that the design can be constructed as designed and therefore minimize the risk of change orders; review of proposed change orders for validity and preparation of necessary contract change documents; proactive identification and resolution of potential construction problems; overseeing construction inspectors; testing of mechanical and electrical systems; and acting as a liaison between the City and other parties.
• Construction Logistics Planning, which includes preparing a comprehensive and integrated plan for pedestrian and vehicular traffic and parking controls, site access control, delivery scheduling, accommodation of special events, restrictions on work hours and worker arrival times, constraints on storage and staging of equipment and materials, and community construction notifications and updates.
• Construction Inspection, which includes activities such as inspection of all aspects of the site for conformance with the plans and specifications; oversight of compliance with state and regulatory safety and environmental protection requirements; checking of materials deliveries for compliance with requirements, completion of daily inspection reports, and other record-keeping as needed.
• Material Testing, which includes field and laboratory sampling and testing of materials and products to ensure they meet the contract specifications.
To obtain resources for the above-described services with the necessary expertise, in the necessary amounts, and with the necessary availability, all while considering other projects and activities for which City staff are responsible - the Public Works Department must rely on contract services.
Accordingly, in compliance with the City’s municipal code and the California Government Code, whereby professional services contractors/consultants are selected based on qualifications rather than low-bid, the City issued a Request for Proposals on July 29, 2026, for project management, construction management, and inspection services for the Project. Seven proposals were received by the September 14, 2026, deadline. An evaluation committee consisting of members of the Public Works, Recreation and Parks, and Community Development Departments evaluated these proposals according to the following selection criteria:
• Demonstrated understanding of the services to be provided;
• Proposed personnel’s qualifications and experience performing similar work;
• Approach to the work; and
• Familiarity with similar coastal communities and land use conditions.
The evaluation panel concluded that the proposals of three firms scored in a tier above the remaining proposals. Interviews with the top three firms were conducted on October 19, 2026.
Following the interviews, Brookwood Group, LLC (Brookwood) was scored as the highest-ranking firm by the evaluation committee. Subsequently, staff further refined the scope of services and negotiated the fee with Brookwood. The number of hours for each person proposed for the project was found to be consistent with the number of hours and category of personnel needed to perform the scope of services for a project of this size and complexity. Additionally, the rate for each category of personnel comprising the fee was found to be within the range of rates charged by consultants performing similar services under similar conditions. Therefore, the proposed fee of $3,290,000 was found to be fair and reasonable.
The estimated cost of project management, construction management, and inspection services presented to the City Council on May 12, 2026, was approximately $2,950,000. The Brookwood base fee is approximately $2,990,000, which is nearly the same as the previous estimate. However, the proposed fee also includes a contingency of 10%, or approximately $300,000, for use only with prior staff authorization for any unforeseen circumstances, which was not included in the prior estimate. After reviewing similar recent construction projects in the region, staff now believes that it is important to include a contingency, as there are typically unforeseen circumstances on projects of this size and complexity. There are sufficient CIP funds in the project budget to move forward with the total fee, including contingency, at this time. It is unknown if additional funding will be needed for construction until construction bids are received.
Therefore, staff recommends that City Council approve a project management, construction management, and inspection services agreement for $3,290,000 to Brookwood Group, LLC for the Senior and Scout Community Center Project.
Next Steps
Following the approval of the Project Management, Construction Management, and Inspection Services Agreement, Brookwood will begin the work of preparing the project for construction bidding.
In addition to the services being provided by Brookwood, an architect/engineer must remain engaged in the project through the end of construction. This is because of the need to visit the site to ensure construction conforms to design intent; review construction contractor submittals for conformance with plans and specifications; respond to requests for design clarifications from the construction contractor; and issue design revisions necessitated by unknown field conditions. Therefore, staff will present a proposed professional services agreement with Tomaro for architectural and engineering construction administration services at a future date for the City Council’s consideration.
The following is the anticipated schedule for key milestones to take the Project to completion:
• Construction Documents Review: December 2026 - March 2027
• Construction Bid Package Preparation: March 2027 - May 2027
• Construction Bidding: May 2027 - August 2027
• Construction Contract Award: September 2027
• Construction Start: November 2027
• Construction Completion: December 2029
• Closeout: December 2029 - May 2030
Additionally, staff continues to work with Friends on completing a memorandum of understanding (MOU) regarding funding construction of the Project and use of the new facility. The MOU is expected to be presented to the City Council in January 2027 for consideration.
PUBLIC OUTREACH:
On April 20, 2022, a community meeting was held at the Joslyn Community Center to inform the public about the project. The Friends and the architect (Louie Tomaro) were present to answer questions related to the project. The meeting was attended by 22 people.
On May 1, 2023, a second community meeting was held at the Joslyn Community Center to inform the public about the project and its current status. The Friends, the architect (Louie Tomaro), the environmental consultant (Michael Baker International), and City staff were present to answer questions about the project. The meeting was attended by 17 people.
A public notice for the Planning Commission August 23, 2023, public hearing was published in The Beach Reporter, mailed to all property owners and residents within a 500-foot radius of the project site, posted at City Hall and on the City’s website, and sent to all interested parties.
On May 5 and May 12, 2026, the project and project budget were discussed extensively during the presentation of the Proposed Five-Year Capital Improvement Program (CIP) for Fiscal Year 2026-2027 through Fiscal Year 2030-2031 to City Council. The City Council received public comment during these meetings.
On June 2, 2026, the project and project budget were discussed during the public hearing for the Proposed Five-Year Capital Improvement Program (CIP) for Fiscal Year 2026-2027 through Fiscal Year 2030-2031 to City Council. City Council adopted the CIP with modifications for funding the project at this meeting.
A dedicated project webpage (www.manhattanbeach.gov/scouthouse <http://www.manhattanbeach.gov/scouthouse>) exists to keep the public informed with periodic updates including information on the project background, budget, schedule, and consultants working with the City. Furthermore, once the project progresses to the construction phase, public outreach will include construction update notices, message boards, social media coordination, and updates on the City’s website.
ENVIRONMENTAL REVIEW:
The environmental review was completed when the project planning entitlement application was presented to the Planning Commission on August 23, 2023. A CEQA Class 32 Categorical Exemption Report was presented that was prepared in accordance with the California Environmental Quality Act (CEQA), to disclose and evaluate short-term construction-related and long-term operational impacts of the Senior and Scout House Project. Based on this report, the determination of a Categorical Exemption pursuant to Section 15332 (In-Fill Development Projects) of the State CEQA Guidelines was made.
Given that the existing conditions and project scope have not changed since the time the determination was made, and that the requests outlined in Resolution No. 26-0123 (Attachment) do not involve any change to the approved scope of the project and rather involve administrative and financial amendments to the project. As such, this request does not constitute a “project” as defined in Section 15378 of the State CEQA Guidelines. Pursuant to Section 15060(c)(3) of the State CEQA Guidelines, the administrative and financial request is not subject to CEQA, and no additional environmental review is required.
LEGAL REVIEW:
The City Attorney has approved the agreement as to form.
ATTACHMENTS:
1. Resolution No. 26-0123
2. Agreement - Brookwood Group, LLC
3. Building Layout
4. Budget and Expenditures Summary
5. Location Map