SUBJECT:Title
Progress Payment No. 5 in the amount of $180,455.95 to Vido Samarzich, Inc. for the Fiscal Year 2012-13 Water Main Replacement and Fire Hydrant Installation Project (Area 1, Hill Section; 8th, 9th, 10th, 11th and John Streets; and Highview, Pacific and Poinsettia Avenues).
APPROVE
Line
_____________________________________________________________________
Recommended Action
RECOMMENDATION:
Staff recommends that the City Council approve Progress Payment No. 5 in the amount of $180,455.95 to Vido Samarzich, Inc. for the Fiscal Year 2012-13 Water Main Replacement and Fire Hydrant Installation Project (Area1) [95% ($171,433.15) would be released immediately and 5% ($9,022.80) would be retained and released after project completion].
Body
FISCAL IMPLICATIONS:
Water Enterprise Funds in the amount of $1,200,000 were appropriated by City Council through the Fiscal Year 2011-12 and 2012-13 Capital Improvement Plans. An additional appropriation in the amount of $320,000 was approved by City Council on August 7, 2012, bringing total project appropriations to $1,520,000. Anticipated expenditures total to $1,390,490 which will leave an anticipated balance of $129,510 upon completion of the project. Please see Attachment 1, Table 1 for budget, anticipated expenditure and progress payment details in tabular format.
BACKGROUND:
This project is part of the City's annual water main replacement program which replaces old and/or undersized water mains. These main replacements will reduce the risk of main breaks and will enhance fire suppression flows.
As part of the Fiscal Year 2012-2013 Water Main Replacement and Fire Hydrant Installation (Area 1) Project, new 6 and 8 diameter ductile iron pipes are being installed to replace 6,350 lineal feet of existing water main in the streets in the Hill Section of the City shown in Attachment 1, Table 2 and on the location map provided as Attachment 2. All fire hydrants attached to these water mains are being replaced as well. An additional benefit that the project provides is the elimination of three dead-end water mains. Elimination of these dead-end mains will reduce maintenance efforts required to maintain water quality.
On October 4, 2012, City Council awarded a construction contract to Vido Samarzich, Inc. in the amount of $1,059,500 for the Fiscal Year 2012-13 Water Main Replacement and Fire Hydrant Installation Project and authorized the City Manager to approve additional work in the amount of $105,950 (10% of contract amount).
DISCUSSION:
Construction started on November 11, 2012. The contractor has completed installation of all mainline pipes. The pipe has been tested, disinfected and connected to the existing water system. The contractor has connected the new main to individual property water meters. The contractor is currently performing grinding and capping as well as final restriping of the project area's streets.
The contractor has submitted an invoice for Progress Payment No. 5 in the amount of $180,455.95 for work completed to date. Public Works staff has verified that the work was completed in compliance with the contract plans and specifications. Five percent retention ($9,022.80) will be retained and a net progress payment in the amount of $171,433.15 will be released upon City Council approval of this progress payment. Retention will be released after City Council acceptance of the completed project.