Legislation Details

File #: 26-0600    Version: 1
Type: *Gen. Bus. - Staff Report Status: Agenda Ready
In control: City Council Regular Meeting
On agenda: 12/1/2026 Final action:
Title: Update for Underground Utility Assessment Districts 19-12 and 19-14 (No Budget Impact) (Public Works Director Awwad). (Estimated Time: 30 Mins.) RECEIVE AND FILE
Attachments: 1. Location Map, 2. Project Progress Comparison Exhibit, 3. PowerPoint Presentation
Date Ver.Action ByActionResultAction DetailsDetailsVideo
No records to display.

TO:

Honorable Mayor and Members of the City Council

 

THROUGH:

Talyn Mirzakhanian, City Manager

 

FROM:

Ramzi Awwad, Public Works Director

Gilbert Gamboa, City Engineer

Justin Murray, Engineering Technician II

                     

SUBJECT:Title

Update for Underground Utility Assessment Districts 19-12 and 19-14 (No Budget Impact) (Public Works Director Awwad).
(Estimated Time: 30 Mins.)

RECEIVE AND FILE

Body

_________________________________________________________

 

RECOMMENDATION:

Staff recommends that the City Council receive and file the update on Underground Utility Assessment Districts 19-12 and 19-14 (Districts 12 and 14).

 

EXECUTIVE SUMMARY:
Underground Utility Assessment Districts 12 and 14 have advanced substantially since the City Council’s October 2025 update. Most private properties are now either connected to underground electrical service or have completed the City inspection approval process and are awaiting final connection by Southern California Edison (SCE). Significant progress has also been made on underground telecommunications connections and the removal of overhead facilities.

 

As of November 2026, 356 of the 460 properties are converted/connected to underground electrical service, 55 are released/approved by the City for SCE connection, 46 are not released/approved for SCE connection because additional private property work or coordination remains, and three are currently identified for City-managed conversion/connection.

 

Since the October 2025 City Council update, the number of properties connected to underground electrical service has increased by 88, while the number of properties not approved for SCE connection decreased from 109 to 46. Overall, the percentage of properties either connected to underground service or approved by the City for SCE connection has increased from approximately 74 percent to 89 percent. City staff continues to work directly with private electrical contractors and SCE to resolve outstanding issues, advance inspection releases/approvals, and coordinate final underground electrical connections.

 

Spectrum and Frontier have each connected an estimated 98 percent of their customers to underground telecommunications service, a significant advancement since the prior update. Spectrum has begun removing overhead facilities, with removal confirmed from approximately 45th Street south to Shell Street. Spectrum also reports that its underground system is active from 45th Street to Seaview Street, and staff continues to coordinate the schedule for remaining overhead removal. Frontier is preparing to begin overhead removal as well. Meanwhile, staff is preparing to advertise a City construction package primarily for the replacement of five City-owned streetlights and remaining public right-of-way improvements.

 

Rather than waiting for districtwide completion of each phase, staff is advancing the remaining work concurrently wherever conditions allow. Private electrical connections and telecommunications removal are continuing while staff prepares for City streetlight construction and coordinates with SCE on phased pole removal, allowing work to progress in areas that are ready without waiting for every property in both districts to be completed.


FISCAL IMPLICATIONS:

There are no fiscal implications associated with the recommended action.

 

BACKGROUND:

Underground Utility Assessment District (UUAD) Formation

Property owners seeking to place overhead electrical and telecommunications facilities underground typically do so by establishing underground utility assessment districts (UUAD).

 

The first step in establishing a UUAD is for interested property owners to outline proposed district boundaries based on neighborhood support. This step also involves working with City staff to make sure the proposed boundaries are technically feasible based on utility company requirements.

 

The next step is for proponents of the proposed UUAD to circulate petitions among property owners within the boundaries, using preliminary cost estimates developed by the City with input from the participating utility companies. There are two different thresholds for petitions based on the funding approach. Under one approach, the City advances preliminary engineering and assessment costs and is then reimbursed if the district is ultimately formed. For this approach, proponents must obtain signatures from at least 66 percent of the parcel owners within the proposed district. Under another approach, participating property owners pay for preliminary engineering and assessment costs up front, taking on the risk themselves if the district does not ultimately form. For this approach, proponents must obtain signatures from owners representing at least 50 percent of the proposed district’s land area. Petition signatures serve to demonstrate preliminary support; however, a formal assessment vote still occurs later through the Proposition 218 balloting process.

 

If a petition meets the support threshold, the proposed UUAD is then presented to the City Council for a determination on whether it should advance to the design stage. If the City Council approves proceeding with the UUAD, the next step is for the utility companies to prepare engineered plans for undergrounding of the main overhead utility infrastructure along the public right-of-way. The engineered plans include the main line, vaults, and handholes, as well as the proposed service lines which connect the main system to the private panels. Although the plans may depict the intended service line connections, property owners are responsible for installing the service line connections on their private property.

 

Once the engineered plans are finalized, the utility companies will solicit construction bids to determine the cost of installing the main line and ancillary components described above. Subsequently, an Assessment Engineer prepares an Engineer's Report that allocates the cost of the main underground infrastructure (and other associated costs, such as engineering and financing) to individual properties based on the special benefit each property receives. This cost does not include the additional costs that private property owners will bear for underground service lines connecting to the main line, as well as any other private property work that may be needed to connect to a new underground system (such as panel upgrades).

 

Following City Council approval of the Engineer’s Report, property owners receive ballots with their proposed assessments pursuant to the Proposition 218 process. A public hearing is then held, during which ballots, weighted according to each property's proposed assessment, are counted. If more than 50 percent of the weighted ballots returned support the proposal, the City Council may adopt a resolution formally establishing the district.

 

Once formed, a district’s main underground infrastructure is funded through the aforementioned property owner assessments, paid upfront or financed through City-issued bonds. Once funding is secured, utility companies and their contractors obtain the necessary City permits and construct the main underground infrastructure.

 

Following construction of the underground infrastructure in the public right-of-way, the City notifies affected property owners of their responsibility to install their underground service lines and complete other improvements so they can connect their property to underground service. Property owners separately hire and pay private contractors to do this work. The City's Building & Safety Division administers the required electrical permits, inspections, and ultimately provides approval for the electric company to proceed with the final underground service connection.

 

Next, the utility companies install their underground wires and equipment within the main system and activate their underground systems. Then, the utility companies complete individual service connections to private properties as each property owner completes their private property work and passes inspection. Once the necessary private underground service connections have been made, the final step is for utility companies to remove the overhead lines and poles, and replace streetlights when needed. Some activities may occur concurrently, and overhead removal may proceed in phases as individual locations become ready.

UUADs 12 and 14

UUADs 12 and 14 were formed in 2019 following successful Proposition 218 balloting to underground overhead utilities in the El Porto area (see Attachment).

 

Construction of the main line underground system in the public right-of-way began in 2020 and was substantially completed in 2021. As described earlier in this report, this meant that the underground infrastructure was in place but did not mean that the utility systems were fully installed or operational. Property owners were notified in 2021 to install underground private service lines, complete all other needed improvements on their property, and begin connecting to the main underground system. Meanwhile, the utility companies were installing underground wires as well as other equipment, and activating their underground systems to accommodate the new underground service connections.

 

On October 21, 2025, staff presented an update to the City Council stating that the completion of the remaining private property underground service lines and connections was the primary focus. The update provided a schedule that anticipated completion of the private connections by May 2026, followed by overhead pole and wire removal, streetlight installation, and final closeout. However, as the private property connection period stretched on, some electrical permits expired or required extensions while property owners were still completing work or awaiting utility coordination. To reduce the resulting fees and remove an administrative barrier to completion, the City Council directed staff to return with a fee-waiver proposal and, on November 4, 2025, adopted Resolution No. 25-0125 authorizing a waiver and refund program for qualifying electrical permits in UUADs 12 and 14.


DISCUSSION:

Current Status of Electrical Undergrounding

As of November 2026, the electrical conversion status of the 460 active properties receiving power from Southern California Edison (SCE) in UUADs 12 and 14 is as follows.

•                     Converted/Connected: 356 properties (77 percent) are connected to underground electrical service.

•                     Released/Approved for Connection: 55 properties (12 percent) have completed the required private electrical conduit and panel work, passed the City’s Electrical Release inspection, and are awaiting final SCE connection.

•                     Not Released/Not Approved for Connection: 46 properties (10 percent) require additional work, inspection, or utility coordination before the City can release them to SCE.

•                     City to Convert: 3 properties (1 percent) are identified for City-managed private conversions. The required work remains outstanding and the City is coordinating the steps necessary to complete those connections.

 

The above figures do not include 11 properties that are completing their underground connection process separately as part of redevelopment.

The following summarizes changes in electrical conversion status since the October 2025 City Council update. For consistency, percentages are based on active properties and exclude those undergoing redevelopment:

•                     Converted/Connected: Increased from 268 properties (58 percent) to 356 properties (77 percent).

•                     Released/Approved for Connection: Decreased from 72 properties (16 percent) to 55 properties (12 percent).

•                     Not Released/Not Approved for Connection: Decreased from 109 properties (24 percent) to 46 properties (10 percent).

•                     No Work Started: No properties remain in this classification.

•                     City to Convert: 3 properties (1 percent) remain in this classification.

 

Overall, the percentage of properties either Converted or Released increased from approximately 74 percent to 89 percent.

 

Properties for City to Convert

Private property owners are generally responsible for completing their underground conversions. However, in limited cases where a property owner fails to take the necessary actions to complete their private connection work despite ongoing outreach and coordination, and the resulting delay impedes overall project completion, the City may directly intervene and manage the private connection work. Three properties are currently identified for City-managed conversion/connection, down from five in late 2025 after two property owners agreed to proceed with their own private conversions/connections. Staff is also monitoring up to six additional properties categorized as not released/not approved for connection. These properties may require City involvement if there continues to be a lack of progress that impedes completion of the overall undergrounding project.

 

Staff notes that City-managed conversions are a last resort because they are very complicated, require significant unplanned City resources, and are typically more costly for individual property owners. The City will seek recovery of costs advanced for private conversions from the benefiting property owners, as provided by the Manhattan Beach Municipal Code.

 

Los Angeles County Beaches and Harbors Facility

The Los Angeles County Beaches and Harbors lifeguard/maintenance building at the west end of Rosecrans Avenue is a unique remaining connection because it is a public County facility rather than a typical residential property. Since the October 2025 update, SCE has identified replacement service equipment that must be installed before the final connection can be completed, and City staff is currently assisting County Beaches and Harbors with the electrical permit so the remaining work can proceed to final SCE connection.

 

 

Current Status of Telecommunications Undergrounding

Telecommunications work has advanced considerably since the prior City Council update, with significant progress in underground service connections, resolution of public right-of-way deficiencies, and the commencement of overhead facility removal. Based on current coordination, Spectrum and Frontier have each connected an estimated 98 percent of resident services to underground facilities. For Spectrum, this represents a substantial increase from approximately 20 percent of homes connected to underground service at the October 2025 City Council update. The relatively few remaining connections involve individual property conditions, while removal of the overhead telecommunications lines is progressing separately.

 

Spectrum has coordinated with the City to investigate and address isolated underground conduit issues and began removing overhead facilities in September 2026. Spectrum confirmed removal from approximately 45th Street south to Shell Street. Its underground system is active from 45th Street south to Seaview Street. Overhead removal is proceeding in phases as Spectrum coordinates the remaining underground service connections and physical removal of overhead facilities.

 

Frontier has also made significant progress in resolving underground conduit deficiencies identified throughout both districts and is preparing to advance its overhead removal work. Beginning in March 2026, Frontier undertook extensive corrective work in the public right-of-way, including additional issues identified during field investigations. Most of the identified corrective work that could be performed with available access has been completed, substantially reducing the need for City-contracted repairs. The remaining locations primarily involve private property conditions or access limitations that Frontier is coordinating as it prepares to transition the services from overhead to underground.

 

City Efforts to Advance Completion

As the project advances toward completion, staff is focusing on the remaining properties requiring individualized coordination. To maintain progress and address outstanding issues, the City continues several ongoing efforts:

•                     Property tracking and transparency: Maintaining detailed property-level records and the City's interactive property status map to monitor connection progress, identify outstanding requirements, and provide residents with access to current property status information.

•                     Direct contractor coordination: Conducting regular field meetings with private electrical contractors to address outstanding work, coordinate inspections and corrections, and facilitate contractor participation during SCE's final electrical connections.

•                     Utility coordination: Holding biweekly meetings with SCE and coordinating regularly with Spectrum and Frontier to address pending service connections, resolve property-specific issues, and advance overhead removal and pole removal wherever conditions permit.

•                     Individual property owner assistance: Serving as a point of contact for residents, helping clarify outstanding requirements, and working directly with contractors, utility companies, and Building & Safety on their behalf to resolve issues and facilitate remaining connections.

 

Obstacles to Completion

Despite substantial progress, the completion of the remaining underground electrical connections is still constrained by utility scheduling limitations, private contractor availability, and property-specific conditions requiring individualized coordination. These challenges have become increasingly important as the project advances toward completion.

 

Scheduling final underground electrical connections with SCE remains a primary constraint. SCE has limited availability for conversion appointments, and scheduled connections are sometimes canceled or rescheduled due to competing operational demands. Because SCE controls the scheduling and performance of its final service connections, properties that have completed their private electrical work and received City approval may still experience delays before being connected to underground service.

 

Contractor availability presents a related challenge. Much of the private electrical work in both districts is performed by a relatively small number of contractors who are also committed to other projects. Final SCE connections often require coordination and on-site participation by these same contractors. However, time spent supporting SCE connections may not be compensated separately in the same manner as private electrical work. Contractors must therefore balance supporting scheduled SCE connections with completing additional private property improvements needed to obtain City approval for other properties. Cancellations and rescheduling can further disrupt contractor availability, affecting both the completion of approved connections and progress on remaining private work.

 

Additionally, many of the remaining properties require individualized solutions involving electrical corrections, underground conduit conditions, access limitations, or outstanding owner-contractor arrangements. These conditions can require more extensive coordination than earlier conversions. Staff continues to work directly with SCE, private contractors, and affected property owners to resolve these issues, coordinate connection opportunities, and advance work wherever conditions permit.

 

Project Schedule and Next Steps

The October 2025 project schedule anticipated completion of private property connections by May 2026, overhead wire and pole removal by November 2026, streetlight installation by February 2027, and final closeout by May 2027.

 

The May 2026 private property connection milestone was not achieved, and overhead removal is progressing in phases beyond the originally anticipated schedule. Staff continues to work toward May 2027 as the overall project closeout target. This remains a planning target, subject to completion of outstanding private property work, contractor availability, utility scheduling, and the remaining City construction activities.

 

Although the City coordinates the overall project, its direct responsibilities include permitting and inspections, property tracking, public outreach, and City-managed construction. Property owners and their contractors are generally responsible for completing private property connections, while the utility companies control the scheduling and performance of their respective service connections and overhead facility removal. While the City cannot directly control these activities, staff continues to actively influence their progress through direct coordination with the responsible parties, resolution of property-specific obstacles, and efforts to improve conversion scheduling and advance overhead removal.

 

PUBLIC OUTREACH:
Since the October 2025 City Council update, staff has continued direct outreach through project notices, email and telephone correspondence, field coordination, and the City’s interactive property status map. Additional notices were issued in March 2026 regarding Spectrum decommissioning and SCE and Frontier right-of-way work. Staff continues to provide individualized assistance to property owners and will continue publishing significant project milestones as overhead removal progresses.


ENVIRONMENTAL REVIEW:
The recommended action is administrative in nature and does not constitute a “project” under the California Environmental Quality Act (CEQA) as defined in Section 15378(b)(5) of the CEQA Guidelines. Therefore, it is not subject to environmental review.


LEGAL REVIEW:
The City Attorney has reviewed this report and determined that no additional legal analysis is necessary.

 

ATTACHMENTS:
1. Location Map

2. Project Progress Comparison Exhibit
3. PowerPoint Presentation