Title: Final Payment in the Net Amount of $71,901.90 to John S. Meek Company; Formally Accept the Manhattan Beach Pier Localized Structural Rehabilitation Project as Complete; and Authorize Filing of the Appropriate Notice of Completion and Release Retention in the Amount of $26,536.37 APPROVE
Attachments: 1. Attachment 1 - Budget, Expenditures and Change Orders
TO:
Honorable Mayor Powell and Members of the City Council

THROUGH:
David N. Carmany, City Manager

FROM:
Jim Arndt, Public Works Director
Steve Finton, City Engineer
Edward Kao, Senior Civil Engineer

SUBJECT: Title
Final Payment in the Net Amount of $71,901.90 to John S. Meek Company; Formally Accept the Manhattan Beach Pier Localized Structural Rehabilitation Project as Complete; and Authorize Filing of the Appropriate Notice of Completion and Release Retention in the Amount of $26,536.37
APPROVE
Body
____________________________________________________________________
RECOMMENDATION:
Staff recommends that the City Council authorize the City Manager to:
a) Approve the issuance of a final payment in the net amount of $71,901.90 to John S. Meek Company for the Manhattan Beach Pier Localized Structural Rehabilitation Project;
b) Formally accept the Manhattan Beach Pier Localized Structural Rehabilitation Project as complete; and,
c) Authorize filing of the appropriate Notice of Completion and the release of retention in the amount of $26,536.37.

FISCAL IMPLICATIONS:
City Council appropriated State Pier and Parking Funds in the amount of $500,000 for this project through the fiscal year 2011-2012 Capital Improvement Plan. See Attachment 1, Tables 1, 2 and 3 for tabulated budget, expenditure and change order details. A summary of project funding and expenditures is as follows:

Budget $500,000
Construction (John S. Meek Company) $265,363.68
Design and inspection services $108,900
Miscellaneous costs $715
Total Project Costs $374,978.68
Balance of appropriations $125,021.32

BACKGROUND:
The Manhattan Beach Pier is a reinforced concrete recreational structure constructed between 1917 and 1920. In the 1950s, the County of Los Angeles completed a major repair project where pneumatically placed concrete was placed on areas showing deterioration. This project resulted in an almost freeform shape of the piles and girders. In the 1980s, corrosion in the rei...

Click here for full text